Question

How does the cost per equivalent unit of conversion cost in beginning Work-in process inventory compare...

How does the cost per equivalent unit of conversion cost in beginning Work-in process inventory compare to the cost per equivalent unit of conversion cost added for the month of October?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:-

Under the FIFO method, we will calculate equivalent units for 3 things: Units completed from beginning work in process, units started and completed this period and units remaining in ending work in process. This video will discuss the differences between the Weighted Average and FIFO methods for equivalent units (if you are comfortable with the weighted average method, skip to minute 4:06 to begin the discussion on the FIFO method).

Equivalent units for the period will be calculated as follows under FIFO (keep in mind, you may have different percent complete for materials, labor and overhead):

  1. Units from beginning work in process: you want to complete this units, so how much MORE effort will be needed to finish these units. You will calculate this as beginning work in process units x (100% – given % complete) to calculate the amount of additional work necessary to make the unit 100% complete.
  2. Units started and completed this period: take the units x 100% complete since they were started and completed they have received all of their materials, labor and overhead and will not receive any more since they are finished.
  3. Units in Ending work in process: just like with the weighted average method, we will take the ending work in process units x a given % complete.

Under the weighted average method, we use beginning work in process costs AND costs added this period. Under the FIFO method, we will only use the costs added this period. This video will explain the differences between the two approaches.

The formula we will use for calculating cost per equivalent unit under the FIFO Method is:

Current Costs added this period
÷ Total Equivalent Units
= Cost per Equivalent Units
Add a comment
Know the answer?
Add Answer to:
How does the cost per equivalent unit of conversion cost in beginning Work-in process inventory compare...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Calculate the cost per equivalent unit of material and conversion cost for January - using the...

    Calculate the cost per equivalent unit of material and conversion cost for January - using the Weighted Average Approach Units Materials Conversion Work in process January 1 2,500 50% 35% Work in process January 31 45% 25% Materials cost in work in process January 1 $25,000 Conversion costs in work in process January 1 $10,000 Units started in production 12,000 Units transferred to the next department 8,000 Materials cost added during January $20,000 Conversion costs added during January $7,500 Complete...

  • What is the unit cost per equivalent unit of beginning inventory in Department​ A? (Round the...

    What is the unit cost per equivalent unit of beginning inventory in Department​ A? (Round the final answer to the nearest whole​ dollar.) Charlie Chairs Inc., manufactures plastic moldings for car seats. Its costing system utilizes two cost categories, direct materials and conversion costs. Each product must pass through Department A and Department B. Direct materials are added at the beginning of production. Conversion costs are allocated evenly throughout production. Data for Department A for February 2017 are: Work in...

  • the cost per equivalent unit for conversion costs for the first department for the month is...

    the cost per equivalent unit for conversion costs for the first department for the month is closest to: Heller Corporation uses the weighted average method in its process costing system.D first processing department for the most recent month are listed below: in its process costing system. Data concerning the Beginning work in process inventory: Units in beginning work in process inventory ........... Materials costs......... Conversion costs...................... Percent complete with respect to materials........ Percent complete with respect to conversion...... Units started...

  • 2. Compute both the direct material cost and the conversion cost per equivalent unit. ork Saved...

    2. Compute both the direct material cost and the conversion cost per equivalent unit. ork Saved Help Required information Problem 16-2A Weighted average: Cost per equivalent unit; costs assigned to products LO C2, C3 (The following information applies to the questions displayed below.) Victory Company uses weighted average process costing to account for its production costs. Conversion cost is added evenly throughout the process. Direct materials are added at the beginning of the first process. During November, the first process...

  • Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...

    Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $750 and $120, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 0 80 Started and completed during October 3,700 3,700 Transferred out of Rolling (completed) 3,700 3,780 Inventory in process, October 31 300 75 Total units to be...

  • Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...

    Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $0.85 and $2.20, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 3,400 Started and completed during October 67,000 67,000 Transferred out of Rolling completed) 67,000 70,400 Inventory in process, October 31 7,000 4,200 Total units to be assigned...

  • Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...

    Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $0.50 and $1.65, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 0 3,200 Started and completed during October 46,000 46,000 Transferred out of Rolling (completed) 46,000 49,200 Inventory in process, October 31 5,000 2,500 Total units to be...

  • Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...

    Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $1.05 and $0.95, respectively, The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 2,600 Started and completed during October 64,000 Transferred out of Rolling (completed) 66,600 64,000 64,000 3,000 67,000 Inventory in process, October 31 1,200 Total units to be...

  • Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...

    Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $1.55 and $0.60, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 0 3,000 Started and completed during October 38,000 38,000 Transferred out of Rolling (completed) 38,000 41,000 Inventory in process, October 31 5,000 3,000 Total units to be...

  • Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of...

    Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $1.45 and $0.95, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion 0 Inventory in process, October 1 Started and completed during October Transferred out of Rolling (completed) Inventory in process, October 31 5,600 70,000 70,000 70,000 6,000 75,600 2,400 78,000 Total units to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT