Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years.
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash flow: | –$1,700 | $630 | $690 | $660 | $440 | $240 |
compute payback in years
Payback Period is the time in which initial investment comes back as inward cash flow.
Payback Period = 1(630) + 1(690) + 0.57(380/660)
Payback Period = 2.57 years
Discounted Payback Period,
Year 1, 630/1.07 = $588.78
Year 2, 690/(1.07)2 = $602.67
Year 3, 660/(1.07)3 = $538.75
Year 4, 440/(1.07)4 = $335.67
Discounted Payback Period = 1(588.78) + 1(602.67) + 0.944(508.55/538.75)
Discounted Payback Period = 2.944 years
Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $660 $640 $420 $220 Payback years
Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: 0 -$2,300 1 $870 2 $870 3 $780 4 $560 5 $360 Payback years Should the project be accepted or rejected? accepted O rejected
Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: 0 -$2,300 1 $870 2 $870 3 $780 4 $560 5 $360 Payback years Should the project be accepted or rejected? accepted O rejected
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: -$2,800 $1,070 $1,020 $889 $660 $460 Payback years Should the project be accepted or rejected? accepted rejected
Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: S Cash flow: o $2,900 1 $1,110 2 $1,050 3 $900 4 $680 5 $480 Payback years
Compute the discounted payback statistic for Project if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project t Timet Cash flow: -51,600 $720 $660 Discounted payback period Should the project be accepted or rejected accepted rejected
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow –$12,400 $3490 $4460 $1800 $0 $1280 Payback years
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: Cash flow: 0 -$12,500 1 $3,500 2 $4,480 3 $1,820 4 $0 5 $1,300 Payback years Should the project be accepted or rejected? accepted rejected
Compute the payback statistic for Project B if the appropriate cost of capital is 10 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "O" (zero).) Project B Time: Cash flow: -512,900 12 $3,540 $4,560 $1,900 $0 $1,380 Payback years Should the project be accepted or rejected? accepted rejected < Prex 6 of 7 Ners > search OM