Airon Company recently completed 10,600 units of its single product, consuming 32,000 labor hours that cost the firm $480,000. According to manufacturing specifications, each unit should have required 3 hours of labor time at $15.40 per hour. On the basis of this information, determine Airon’s total labor variance.
Total labor variance
= Standard labor cost - Actual labor cost
= (10,600*3*15.40) - 480,000
= 489,720 - 480,000
= 9,720 Favourable
Airon Company recently completed 10,600 units of its single product, consuming 32,000 labor hours that cost...
Dover Enterprises recently used 19,000 labor hours to produce 6,800 completed units. According to manufacturing specifications, each unit is anticipated to take two hours to complete. The company's actual payroll cost amounted to $214,700. If the standard labor cost per hour is $11.2, Dover's labor rate variance is (Do not round intermediate calculations.):
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor vage rate Machine-hours Number of units completed $50,370 420 labor-hours $ 10 per labor-hour 501 machine-hours 3,000 units 4 The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine- hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer...
Job 231 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $ 46,000 630 labor-hours $ 14 per labor-hour 340 machine-hours 2,500 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $10 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $50,870 425 labor-hours $ 13 per labor-hour 506 machine-hours 3,100 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $11 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $58,370 500 labor-hours 10 per labor-hour 581 machine-hours 4,600 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $57,370 490 labor-hours $ 12 per labor-hour 571 machine-hours 4,400 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $52,870 445 labor-hours $ 13 per labor-hour 526 machine-hours 3,500 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $11 per machine- hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to...
Job 243 was recently completed. The following data have been recorded on Its Job cost sheet Direct maperials $56, 370 Direct labor-hours 480 labor-hours Direct labor wage rate 10 per labor-hour Machine-hours 561 machine-hours Number of units completed 4, 200 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate Is $14 per machine- hour. Required: Compute the unit product cost that would appear on the Job cost sheet for this Job. (Round your answer...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 55,870 Direct labor-hours 475 labor-hours Direct labor wage rate $ 11 per labor-hour Machine-hours 556 machine-hours Number of units completed 4,100 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to...
Job 397 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Number of units completed $ 49,000 670 DLHS $ 12 per DLH 2,000 units The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $10 per direct labor-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...