What is earned value management? What are the four main earned value management forecasting formulas? Please describe them with equations
Please give answer in more than 200 words and prefer to paste from word or excel or type as plain text.
Estimate to Complete (ETC)
ETC represents the expected cost required to complete the project. It measures only the future budget needed to complete the project, not the entire budget. It allows the project manager to compare the funding needs to finish the project with funding available. There are two ways to calculate ETC.
1) Based on past project performance:
ETC = (BAC – EV) / CPI
Since each of the input variables (right side of the equation) has been determined prior to this step, the ETC can be calculated either for each task or directly for the whole project.
2) Based on a new estimate
This is called a management etc. This means that a new estimate of the remaining tasks in the project is performed.
Estimate at Completion (EAC)
It can be calculated on a task by task basis or once for the entire project.
1)Future performance will be based on the budgeted cost
This method does not assume the project finishes on budget. Rather it takes into account the one time event and adjusts the whole project plan upward or downward to estimate the final result.
EAC = AC + (BAC – EV)
2)Future cost performance will be based on past cost
performance
If you think the past performance is not unusual and the past
performance is a good indicator of the future, you would use this
formula.
EAC = AC + [(BAC – EV) / CPI]
3)Future cost performance will be influenced by past schedule performance
Since schedule and cost performance are usually related, there could be a reason to adjust the cost performance based on the schedule performance. In the following formula an average of the CPI and SPI are used to extrapolate the final project cost.
EAC = AC + [(BAC -EV) / (CPI x SPI)]
4)A new estimate is produced
In this case a Management ETC can be added to the to-date cost (AC)
to determine the final EAC.
EAC = AC + ETC
Variance at Completion (VAC)
The VAC is a forecast of what the variance, specifically the Cost Variance (CV), will be upon the completion of the project.
In many situations the project manager must request additional funding as early as possible, or at least report the potential for an overrun. The VAC represents the size of this request.
The formula is:
VAC = BAC – EAC
= Old Budget – New Budget
To Complete Performance Index (TCPI)
The TCPI represents the efficiency level, specifically the CPI, that will make the project finish on time. It can be a powerful indicator because it is generally easy to ascertain.There are two ways to calculate the TCPI.
TCPI = (BAC – EV) / (BAC – AC)
TCPI = (BAC – EV) / (EAC – AC)
What is earned value management? What are the four main earned value management forecasting formulas? Please...
NEED ANSWER ASAP Review the following learning objective from the text: Describe four qualitative forecasting techniques. Then, explain why you agree or disagree with the following statement: Knowledge about consumer online purchase behavior is more likely to do is much more valuable than information regarding what customers plan or want to do. ANSWER THROUGHLY, COPY AND PASTE PLEASE NEW ANSWER NEVER USED BEFORE PLEASE!
What is the concept of diminishing returns? Dont copy paste from the websites. Please answer in more than 350 words and only in word format no images. Explain the meaning, concept and then add a conclusion at last. Thanks
What is the main difference between cash and accrual accounting? Why is accrual accounting adopted more widely than cash accounting? (160 words maximum) Explain the concept “depreciation” in your own words. Suppose two companies acquired a same fixed asset at the same time, both of them believe that the useful life of the assets is five years with no residual value. Company A adopts straight-line depreciation method while Company B uses diminishing balance depreciation method at a depreciation rate of...
Case Study Demand Forecasting For an organization to provide customer delight it is important that organization can understand what customer wants and how much do they want. If an organization can gauge future demand that manufacturing plan becomes simpler and cost-effective. The process of analyzing and understanding current and past information to understand future patterns through a scientific and systemic approach is called forecasting. And the process of estimating the future demand of the product in terms of a unit...
use your own words, don't copy and paste, don't use handwriting, please. Question 1 Briefly describe the three main types of software maintenance. Why is it sometimes difficult to distinguish between them? Question 2 What are the strategic options for legacy system evolution? When would you normally replace all or part of a system rather than continue maintenance of the software? Question 3 Discuss at least four risks that could arise in a given software development, analyse each risk according...
please help me solve this problem with excel formulas please and
thank you!!
A financial planning service offers a unique program for parents to save for a child's college education. Starting on the child's 12th birthday, annual deposits are made. The first deposit is $5,000 and the required deposit increases by $1000 each year, until the child's 18th birthday, when the final deposit is made. Beginning on the child's 19th birthday, four annual withdrawals of $10,000 can be made. Assuming...
What are the nutrition statutes in your state or province and
how will these statutes direct your practice as a Specialist in
Fitness Nutrition?
Answer should be at least 250 or more be as detiled and include
the state, province, or other jurisdiction (international students)
where you will be practicing as a Specialist in
FitnesNutrition.
My State is califorina united states
cuyeerthication-courses/final-examination/?product id-231§ion-3 e. Katy Hearn Fit mported From s..imported From sa.. formal email Search Appointme... Ya. Launch Your spor......
Show what formulas are used in excel to solve problems
please.
What role does capital budgeting play in the firm's overall
financial planning program? answer must be at least 300 words.
2 COMMON STOCK VALUATION Crosby Corporation common stock paid $1.32 in dividends last year and is expected to grow indefinitely at an annual 7 percent rate. What is the value of the stock if you require an 11 percent return? 4 6 DATA 7 Growth rate 8 Dividend (Do)...
3. Please describe your willingness to pay for a certain good, in terms of dollars. Given the current price of that good, what is your consumer surplus? Now imagine you run a business that sells a good of your choice. How would you use information on consumer's willingness to pay to determine the price at which you sell your good? Please describe the cost of production, average willingness to pay, and consumer and producer surpluses in your example. 4. In...
please use Excel to answer each question
Questions 1-3 Biff Titan, a student at UWO, plans to open a hot dog stand inside UWO's football stadium during home games. There are eight (8) home games scheduled for the upcoming season. He must pay the UWO athletic department a vendor's fee of $1,600 for the season. The stand and other equipment will cost him $2,850 for the season. Each hot dog will cost him $0.61. He has talked to friends at...