An investment has the following cash flows. Should the project be accepted if it has been assigned a required return of 9.5%? Why or why not?
Year Cash Flow
0 -24,000
1 8,000
2 12,000
3 9,000
|
No; because the IRR is 9.89% |
||
|
Yes; because the IRR exceeds the required return by about 0.39% |
||
|
Yes; because the IRR is less than the required return by about 3.9% |
||
|
Yes; because the IRR is positive |
IRR is the rate at which NPV is 0. At 9.89% NPV comes to 0
| Particulars | 0 | 1 | 2 | 3 | NPV |
| Cash flow | -24000 | 8000 | 12000 | 9000 | |
| PVIF @ 9.89% | 1.0000 | 0.9100 | 0.8281 | 0.7536 | |
| PV | -24000 | 7280 | 9937 | 6782 | 0 |
Thus IRR = 9.89%
Since IRR is greater than required rate of return project should be accepted
Ans : Yes; because the IRR exceeds the required return by about 0.39%
An investment has the following cash flows. Should the project be accepted if it has been...
An investment has the following cash flows. Should the project be accepted if it has been assigned a required return of 14 percent? why or why not? Financial calculator is appropriate here. Year Cash flows -$30,000 $8400 $13,900 $18,600 0 1 2 3 A. No, the IRR exceeds the required return by about 1.08 percent OB. No the IRR is less that the required return by about 0.97 percent C. Yes, the IRR exceeds the required return by about 1.08...
3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent? Year Project A Project B -$80,000 -$80,000 31,000 31,000 0 31,000 110,000 A. accept project A as it always has the higher NPV B. accept project B as it always has the higher NPV C. accept A at 8.5 percent and B at 13 percent D. accept...
Question 24 1 pts You are considering the following two mutually exclusive projects. Which project(s) should be recommended? Project A Project B Year Cash Flow Year Cash Flow 0 $75,000 0 -$70,000 1 $19,000 1 $10,000 2 $48,000 2 $16,000 3 $12,000 3 $72,000 Required rate of return: 10 percent (for A) 13 percent (for B) O accept project B and reject project A. accept both project A and project B. O reject both project A and project B. O...
Your company has a project available with the following cash flows: Year Cash Flow -$81,400 21,350 24,700 30,500 25,850 19,500 If the required return is 14 percent, should the project be accepted based on the IRR? Multiple Choice Yes, because the IRR is 15.82 percent. O Yes, because the IRR is 16.46 percent. O No, because the IRR is 15.19 percent. O Yes, because the IRR is 15.19 percent. C) No, because the IRR is 16.46 percent.
Your company has a project available with the following cash flows: Year. Cash Flow 0. $80,200 1 21,950 2. 25,900 3. 31,700 4. 26,450 5. 20,700 If the required return is 16 percent, should the project be accepted based on the IRR? A. No, because the IRR is 17.75 Percent B. Yes, because the IRR is 18.90 Percent C. No, because the IRR is 18.90 Percent D. Yes, because the IRR is 17.45 Percent E. Yes, because the IRR is...
A proposed project has an initial cost of $38,000 and cash inflows of $12,300, $24,200, and $16,100 for years 1 through 3, respectively. The required rate of return is 16.8 percent. Based on IRR, should this project be accepted? Why or why not? 14 Multiple Choice O No; The IRR exceeds the required return by .58 percent. O No: The IRR is less than the required return by 1.03 percent. O Yes: The IRR exceeds the required return by .58...
IRR Question 3: A project has the following cash flows: Investment today: -$500,000 Cash Flows Years 1-3: $200,000 Cash Flow Year 4: $250,00 Is the IRR of the project less than 20%, between 20% and 25 %, or greater than 25%?
Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...
-Return Analysis Consider the investment project with the net cash flows as shown in the follow- ing table. What would be the value of X if the project's IRR is 23 %? 7s.4 End of Year (n) Net Cash Flow -$12,000 $2,500 $5,500 $X 4 (a) $4,500 (b) $4,750 (c) $6.890 (d) $6,500
A company. has a project available with the following cash flows: Year Cash Flow -$32,150 13.050 14,740 20,780 11,960 AWN- If the required return for the project is 9.5 percent, what is the project's NPV?!