Question

Based on the following table, please create a diagram. Also please calculate and show the ES,...

Based on the following table, please create a diagram. Also please calculate and show the ES, EF, LS, LF times along with the slack for each activity using the critical path methodology.

Required completion is 30 weeks.

Activity

Estimated Time (Weeks)

Actual Finish Time (Weeks)

Immediate Predecessor

A

6

6

B

5

8

C

7

11

a

D

9

9

A

E

4

C,D

F

5

B,D

G

3

B

H

10

E,F,G

Based on your completed network diagram please answer the following questions.

  1. What is the critical path for the project at the end of the planning process?
  2. At the end of the planning process, can the project meet its required completion date? What is its estimated completion date?
  3. Before applying the actual finish times, which activities pose the greatest risk to the project and why?
  4. After applying the actual finish time, identify the activity(s) that should be concentrating on to get the project back on schedule?
  5. What tools would you use to bring it back on schedule once you apply the actuals?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Acitvity ES EF LS LF slack
A 0 6 0 6 0
B 0 5 12 17 12
C 6 13 9 16 3
D 6 15 6 15 0
E 15 19 16 20 1
F 15 20 15 20 0
g 5 8 17 20 12
H 20 30 20 30 0

critical path is ADFH with duration of 30 according to the plan. However, the activities B and C are late by 3 and 4 days respectively. Since C has a slack of 3, and if it gets late by 4 days, it will affect the completion of the project, for which the new critical path will be ACEH with duration of 31, and the project will be delayed by 1 period. B has slack of 12, hence the lateness of 2 days will not affect the project in any way.

Before knowing actual timings, the activities on critical path which are A,D, F and H pose the greatest risk becausedelay in anyone of them causes direct delay to the project duration. The risk is less with the other activities which have slacks.

E and H are the activities which needs to be addressed to bring the project on schedule, by trying to reduce their time somehow by one day ( either of the activities) This can be done by either speeding up the tasks by adding more workers or increasing the working time of resources.

Add a comment
Know the answer?
Add Answer to:
Based on the following table, please create a diagram. Also please calculate and show the ES,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT