|
Activity |
Optimistic(ta) |
Most Likely(tm) |
Pessimistic(tb) |
Predecessor |
|
A |
4 |
5 |
6 |
___ |
|
B |
5 |
6 |
8 |
___ |
|
C |
3 |
4 |
7 |
___ |
|
D |
4 |
5 |
6 |
A |
|
E |
3 |
3 |
3 |
A |
|
F |
3 |
4 |
8 |
B |
|
G |
5 |
8 |
12 |
C |
|
H |
1 |
1 |
1 |
D |
|
I |
1 |
2 |
3 |
E, F |
|
J |
2 |
3 |
6 |
G |
|
K |
4 |
7 |
9 |
I, J |
|
L |
2 |
5 |
7 |
H, K |
a. Find the following:
-Expected Time(te)
-Variance(σ2)
-ES, LS, EF, LF, and S.
-critical path.
b. Find the probability that the project will not be completed in the expected time (CT) + 5 days?

a)

Critical path is the longest path which is C-G-J-K-L having duration 27.5 days
Formula

b)
Expected completion time = duration of critical path = 27.5 days
z = (x-Expected completion time)/project standard deviation
= 5/sqrt(3.638888889)
= 2.62111217
probability of getting the project completed within expected time (CT) + 5 days = NORM.S.DIST(2.62111217,TRUE) = 0.995617829
So, probability that the project will not be completed in the expected time (CT) + 5 days = 1-0.995617829 = 0.004382171
Activity Optimistic(ta) Most Likely(tm) Pessimistic(tb) Predecessor A 4 5 6 ___ B 5 6 8...