Mass Balance Company is manufacturing a new digital scale for use by large chemical companies has come up with a marketing hit. The original production run was for 400 units and these have been produced and shipped. Now, marketing has forecast a demand for an additional 200 units (“if the price is right”). The first scale took 125 hours of direct labor and the second took 110 hours to complete. Per Adam Smith and his academic descendant Professor Culp we will assume the product’s price contains the components material, labor, overhead, and profit at $150/labor hour expended.
USING EXCEL
a)
Direct labor to produce first unit, T1 = 125 hours
Direct labor to produce second unit, T2 = 110 hours
Learning rate, r = T2/T1 = 110/125
= 0.88
----------------------------------------------------
b)
Estimated time for the 600th unit, T600
= T1*rln(600)/ln(2)
= 125*0.889.22882
= 38.42 hours
----------------------------------------------------
c)
Estimated total time to produce the first 400 units is determined by Crawford's formula as shown below

EXCEL FORMULA:

----------------------------------------------------
d)
Total direct labor hours for the first 400 units = 20239.51 hours
Average direct labor hours per unit = 20239.51/400
= 50.6 hours
Average selling price = 50.6*150
= $ 7,590