The following represents a project with known activity times. All times are in weeks.
|
Activity |
Immediate Predecessor |
Time |
|
A |
- |
1 |
|
B |
A |
3 |
|
C |
B |
2 |
|
D |
- |
4 |
|
E |
D |
3 |
|
F |
C, E |
6 |
|
G |
E |
2 |
|
H |
F |
3 |
|
I |
G |
3 |
|
J |
I |
5 |
|
K |
H |
4 |
|
L |
J |
4 |
DEGIJL is the critical path with duration of 21 weeks as given in the diagram given below.
The expected completion date is after 21 weeks from now. The activities on critical path are D,E,G.I,J and L.

| Activity | ES | LS | EF | LF | Slack |
| A | 0 | 1 | 2 | 3 | 2 |
| B | 1 | 3 | 3 | 5 | 2 |
| C | 4 | 6 | 6 | 8 | 2 |
| D | 0 | 4 | 0 | 4 | 0 |
| E | 4 | 7 | 4 | 7 | 0 |
| F | 7 | 13 | 8 | 14 | 1 |
| G | 7 | 9 | 7 | 9 | 0 |
| H | 13 | 16 | 14 | 17 | 1 |
| I | 9 | 12 | 9 | 12 | 0 |
| J | 12 | 17 | 12 | 17 | 0 |
| K | 16 | 20 | 17 | 21 | 1 |
| L | 17 | 21 | 17 | 21 | 0 |
It can be seen that the slack for C is 2 weeks so it can be started latest on week 6.
The following represents a project with known activity times. All times are in weeks. Activity Immediate...