a company implements a new process to create its product and uses 100 hrs to complete...

a company implements a new process to create its product and uses 100 hrs to complete 1 unit. it expects that the new process will be subject to an 80 percent learning curve. if they assume the learning curve will follow the cumulative average time learning model, what is the average time per unit when producing 2 batches?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer- The average time per unit when producing 2 batches = Average time per unit*Learning rate

= 100 hours*80

= 80 hours

Add a comment
Know the answer?
Add Answer to:
a company implements a new process to create its product and uses 100 hrs to complete...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT