I need just the cash flow please
Your company is considering a project which requires an initial investment of $50,000. The equipment has a useful life of six years and you believe the salvage value will be $12000. The project will generate $8000 net income each year for six years. There will be a single mainte- nance expense of $6000 in the third year. Using the present worth method, determine if the project is economically satisfactory. The MARR is 10%. Draw a cash flow diagram for each problem involving cash flows.
NPW of the project = -50000 + 12000 * (P/F,10%,6) + 8000 * (P/A,10%,6) - 6000 * (P/F,10%,3)
= -50000 + 12000 *0.564474 + 8000 *4.355261 - 6000 *0.751315
= -12892.11
As NPW is negative, this project should not be selected
Cash flow Table
| Initial cost | Annual revenue | Maint Cost | Salvage | |
| 0 | -50,000.00 | |||
| 1 | 8,000.00 | |||
| 2 | 8,000.00 | |||
| 3 | 8,000.00 | -6,000.00 | ||
| 4 | 8,000.00 | |||
| 5 | 8,000.00 | |||
| 6 | 8,000.00 | 12,000.00 |
Cash flow diagram

I need just the cash flow please Your company is considering a project which requires an...