Below are 8 stages of a hypothetical system upgrade project.
|
Stage |
Direct predecessor |
Duration |
|
1. Stakeholder buy-in |
10 days |
|
|
2. Define requirements |
1 |
5 days |
|
3. Define scope, schedule, goals, objectives |
2 |
10 days |
|
4. Team formation |
2 |
15 days |
|
5. Development |
3,4 |
70 days |
|
6. Testing |
5 |
30 days |
|
7. Maintenance |
6 |
90 days |
|
8. Closeout |
7 |
5 days |
Work Breakdown Structure for this project:

Gantt Chart:
| GANTT CHART | ||||||||||
| Details | Duration | |||||||||
| Stage | Direct predecessor | Duration | 10 days | 5 days | 10 days | 5 days | 70 days | 30 days | 90 days | 5 days |
| 1. Stakeholder buy-in | 10 days | |||||||||
| 2. Define requirements | 1 | 5 days | ||||||||
| 3. Define scope, schedule, goals, objectives | 2 | 10 days | ||||||||
| 4. Team formation | 2 | 15 days | ||||||||
| 5. Development | 3,4 | 70 days | ||||||||
| 6. Testing | 5 | 30 days | ||||||||
| 7. Maintenance | 6 | 90 days | ||||||||
| 8. Closeout | 7 | 5 days | ||||||||
Below are 8 stages of a hypothetical system upgrade project. Stage Direct predecessor Duration 1. Stakeholder...