Question

avorable variances do not require corrective action or further investigation; only unfavorable variances in performance. Select...

avorable variances do not require corrective action or further investigation; only unfavorable variances in performance.

Select one:

True

False

Projects should be evaluated against standards and by methods established at their completion, including procedures for monitoring, collecting, storing, and evaluating the history of the project.

Select one:

True

False

The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its:

Select one:

A. Slack

B. Float

C. Flex

D. Both A and B

The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its slack.

Select one:

True

False

The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.

Select one:

True

False

The amount of time a project manager estimates it will take to complete the activity under ideal conditions is known as:

Select one:

A. Pessimistic time

B. Optimistic time

C. Likeliest time

D. Utopian time

The objective of feeding buffers is to ensure that non-critical chains are completed so that they do not delay tasks on the critical chain.

Select one:

True

False

The optimistic time is the amount of time the project will take under the worst-case scenario.

Select one:

True

False

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1 : True

Explanation : As favorable variance and unfavorable variance indicated the relationship between the standard and actual price due to which favorable variances do not require corrective action or further investigation.

Answer 2 : True

Explanation : As the final outcome of any project depends upon the effectiveness shown during various stages of project which involves monitoring, storing information, evaluating etc.

Answer 3 : D. Both A and B

Explanation : As activities on its critical path usually has zero slack which is also known as float when the project is been started or when completed.

Answer 4 : True

Explanation : As the slack also known as float provides the project manager required flexibility while starting or completing the project.

Note : Attempted first 4 questions as per HomeworkLib's answering guidelines.

Add a comment
Know the answer?
Add Answer to:
avorable variances do not require corrective action or further investigation; only unfavorable variances in performance. Select...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT