Weldex Industries begins to manufacture a newly designed, small, spot welding machine. The labour hours required for making the second and third units are 29.7 and 28.3 hours respectively.
The labour hours required to manufacture the first unit are close to
32.3 hours
33.9 hours
27.3 hours
30.7 hours
the labour hours required to manufacture the 50th unit are close to
Select one:
17.2 hours
21.2 hours
19.3 hours
20.2 hours
If labour costs are $18/hour, the total labour costs to produce the first four machines are close to
Select one:
$2117
$2071
$2066
$1954

Time for 1st unit = T
Time for 2nd unit = 29.7 = T*(2)^b
Time for 3rd unit = 28.3 = T*(3)^b
Equating the two equations for T and finding b:
29.7/28.3 = 2^b/3^b
1.05*3^b = 2^b
Taking natural Log on both sides
Ln(1.05*3^b) = Ln(2^b)
Ln1.05 + b*Ln3 = b*Ln2
0.04879 + b*1.099 = b*0.693
b = -0.1203
29.7 = T*2^-0.1203
T = 32.3 Hours
1) 32.3
2) Time for 50th unit = 32.3*(50)^-0.1203 = 20.2 hours
3) Time for 4th unit = 32.3*(4)^-0.1203 = 27.3 hours
Time for 1st 4 units = 32.3 + 29.7 + 28.3 + 27.3 = 117.6 hours
Total labor cost = Total time for 1st 4 unit*Labor rate = 117.6*18 = 2117 $
Ans - 2117