You work for Microsoft in their global cell phone group. You
have been made project manager for the design of a new cell phone.
Your supervisors have already scoped the project so you have a list
showing the work breakdown structure and this includes major
project activities. You must plan the project schedule and
calculate project duration. Your boss wants the schedule on his
desk tomorrow morning!
You have been given the information
in Exhibit 5.13. It includes all the activities required in the
project and the duration of each activity. Also, dependencies
between the activities have been identified. Remember that the
preceding activity must be fully completed before work on the
following activity can be started.
Your project is divided into five major
subprojects. Subproject “P” involves developing specifications for
the new cell phone. Here decisions related to such things as
battery life, size of the phone, and features need to be made.
These details are based on how a customer uses the cell phone.
These user specifications are redefined in terms that have meaning
to the subcontractors that will actually make the new cell phone in
subproject “S” supplier specifications. These involve engineering
details for how the product will perform.
The individual components that make
up the product are the focus of subproject “D.” Subproject “I”
brings all the components together, and a working prototype is
built and tested.
Finally in subproject “V,” suppliers
are selected and contracts are negotiated.
Exhibit 5.13: Work Breakdown Structure and Activities for the Cell
Phone Design Project
| MAJOR SUBPROJECTS/ACTIVITIES | ACTIVITY IDENTIFICATION | DEPENDENCY | DURATION (WEEKS) | |
| Product Specifications (P) | ||||
| Market research | P1 | — | 2 | |
| Overall product specifications | P2 | P1 | 4 | |
| Hardware | P3 | P2 | 5 | |
| Software | P4 | P3 | 5 | |
| Supplier specifications (S) | ||||
| Hardware | S1 | P4 | 5 | |
| Software | S2 | P4 | 6 | |
| Product design (D) | ||||
| Battery | D1 | S1 | 2 | |
| Display | D2 | S1 | 1 | |
| Camera | D3 | S1 | 3 | |
| Outer cover | D4 | D1, D2, D3 | 4 | |
| Product integration (I) | ||||
| Hardware | I1 | D4 | 5 | |
| User interface | I2 | D2 | 4 | |
| Software coding | I3 | I2 | 4 | |
| Prototype testing | I4 | I1, I3 | 4 | |
| Subcontracting (V) | ||||
| Suppliers selection | V1 | S1 ,S2 | 12 | |
| Contract negotiation | V2 | I4, V1 | 2 | |
a. Determine the minimum number of weeks for completing the project.
b. Your boss would like you to study the impact of making two changes to how the project is organized. The first change involves using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships within a subproject—all tasks within a subproject would be worked on at the same time and each would take the same amount of time as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V. What would be the expected impact on how long it would take to complete the project if this change were made?
|
a.Minimum number of weeks for completing the project is 39 weeks
b. The time required for project completion wold reduce by 7 weeks to 32 weeks
You work for Microsoft in their global cell phone group. You have been made project manager...