Question

We draw up a precedence relationship among the tasks, based on experience/advice. For example, we are...

We draw up a precedence relationship among the tasks, based on experience/advice. For example, we are told that task C (producing promotional material) can be started only after obtaining copyright permission for images/blurbs to be used and after designing the promotional material.

Task

Description

Immediate Predecessor

Expected Time weeks

A

Author prepares manuscript

None

30

B

Design promotional material

A

6

C

Produce promotional material

B, G

4

D

Copy edit manuscript

A

5

E

Proofread and correct page proofs

D

10

F

Produce final book

E, G

8

G

Obtain legal permission and copyrights

A

14

H

Conduct sales training meeting

C, F

2

  1. Draw diagram.
  2. Expected project completion time in weeks is?
  3. What is the Critical Path?

True or False

  1. The predecessors for F are A, D, E and G?
  2. Tasks C & F cannot be performed simultaneously?
  3. If one person is responsible for both tasks B and D, those tasks would be called independent?
  4. The tasks that determine the overall project duration are A-D-E-F-H?
  5. If ‘D’ is delayed by 2 weeks, the expected project completion time increases by 2 weeks to 57 weeks?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Path Duration
A-D-E-F-H 55
A-B-C-H 42
A-G-C-H 50
A-G-F-H 54

Expected project completion time = Duration of the longest path = 55 weeks

Critical path is the longest path which is A-D-E-F-H

The predecessors for F are A, D, E and G?

True.

Although E, and G are immediate predecessors and A and D precedes D and G respectively

Tasks C & F cannot be performed simultaneously?

false.

Tasks C & F can be performed simultaneously

If one person is responsible for both tasks B and D, those tasks would be called independent?

False

If one person is responsible for both tasks B and D, those tasks would be called dependent

The tasks that determine the overall project duration are A-D-E-F-H?
True.

A-D-E-F-H is the Critical path

If ‘D’ is delayed by 2 weeks, the expected project completion time increases by 2 weeks to 57 weeks?

True.

As D is a critical activity, delaying D by 2 weeks will increase the expected project completion time by 2 weeks to 57 weeks

Add a comment
Know the answer?
Add Answer to:
We draw up a precedence relationship among the tasks, based on experience/advice. For example, we are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT