We draw up a precedence relationship among the tasks, based on experience/advice. For example, we are told that task C (producing promotional material) can be started only after obtaining copyright permission for images/blurbs to be used and after designing the promotional material.
|
Task |
Description |
Immediate Predecessor |
Expected Time weeks |
|
A |
Author prepares manuscript |
None |
30 |
|
B |
Design promotional material |
A |
6 |
|
C |
Produce promotional material |
B, G |
4 |
|
D |
Copy edit manuscript |
A |
5 |
|
E |
Proofread and correct page proofs |
D |
10 |
|
F |
Produce final book |
E, G |
8 |
|
G |
Obtain legal permission and copyrights |
A |
14 |
|
H |
Conduct sales training meeting |
C, F |
2 |
True or False

| Path | Duration |
| A-D-E-F-H | 55 |
| A-B-C-H | 42 |
| A-G-C-H | 50 |
| A-G-F-H | 54 |
Expected project completion time = Duration of the longest path = 55 weeks
Critical path is the longest path which is A-D-E-F-H
The predecessors for F are A, D, E and G?
True.
Although E, and G are immediate predecessors and A and D precedes D and G respectively
Tasks C & F cannot be performed simultaneously?
false.
Tasks C & F can be performed simultaneously
If one person is responsible for both tasks B and D, those tasks would be called independent?
False
If one person is responsible for both tasks B and D, those tasks would be called dependent
The tasks that determine the overall project duration are
A-D-E-F-H?
True.
A-D-E-F-H is the Critical path
If ‘D’ is delayed by 2 weeks, the expected project completion time increases by 2 weeks to 57 weeks?
True.
As D is a critical activity, delaying D by 2 weeks will increase the expected project completion time by 2 weeks to 57 weeks
We draw up a precedence relationship among the tasks, based on experience/advice. For example, we are...