Question

The following information relates to a project​ (task times are in​ weeks). Use the information to...

The following information relates to a project​ (task times are in​ weeks). Use the information to solve for the critical path and then to determine the probability that the project could be completed within 26 weeks.

Task Preceding Task to tm tp

a none 3 5 7

b a   4 7 10

c a 3 5 7

d b 6 9 12

e c 3 7 11

f d,e 3 4 5

The probability that the project is completed within 26 weeks is?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Please find the solution below,

TE = (to + 4*tm + tp)/6

And

Hence,

Hence, The critical path is ABDF, as shown below.

And the Variance of Critical path activities is, (it is calculated by the sum of variances of activities A, B, D, and F -- The critical path activities.)

Now, the probability of completing the project within 26 weeks is calculated by the formula given below.

First, calculate the Z value and use the Z value to calculate the required probability.

Given,


--> Critical path.

Hence, the probability is 0.734 of completing the project within 26 weeks.

Add a comment
Know the answer?
Add Answer to:
The following information relates to a project​ (task times are in​ weeks). Use the information to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT