If a project is acceptable using the net present value criteria, then it
Group of answer choices
will also be acceptable under the more stringent criteria of the payback period.
will also be acceptable under the less stringent criteria of the payback period.
may or may not be acceptable under the payback period.
will never be acceptable under the payback period.
NPV = -initial investment + PV of future cash flows
Present value = Future value/(1+i)^n
i = interest rate per period
n= number of periods
payback period is time taken to recover initial investment
NPV can be high and majority of cash flows can be towards the end of the project, which will increase the payback period
hence may or may not be acceptable under the payback period.
If a project is acceptable using the net present value criteria, then it Group of answer...