An assembly process has a cycle time of 45 seconds and operates with 100 stations. Assuming...

An assembly process has a cycle time of 45 seconds and operates with 100 stations.

Assuming the process starts empty and is machine-paced, how long will it take (in minutes) to complete 50 units? (Round your answer to 2 decimal places.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The first unit will take 45*100 = 4500 seconds and remaining 49 units will have a cycle time of 45 seconds

So, it will take 4500+49*45 = 6705 seconds or 6705/60 = 111.75 minutes to complete 50 units

Add a comment
Know the answer?
Add Answer to:
An assembly process has a cycle time of 45 seconds and operates with 100 stations. Assuming...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT