Analytics Exercise 9-1
Recently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time phased requirements planning.
Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram shown below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly. Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop.
The manufacturing lead times required to produce the gear box and input shaft components are also indicated in the bill-of-material diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts that are needed for the production of gear boxes in a given week must be delivered to the Subassembly Department stockroom before Monday morning of that week.
In preparing the MRP example Phil planned to use the worksheets shown below and to make the following assumptions:
1 Twenty five gear boxes are on hand at the beginning of Week 1, and seven gear boxes are currently on order to be delivered at the start of Week 2.
2 Fifty input shafts are on hand at the start of Week 1, and 26 are scheduled for delivery at the beginning of Week 2.
a. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot.
Gear Box Requirements
| Week: | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| Gross Requirements | 18 | 5 | 12 | 10 | 0 | 20 | 25 | 13 | 0 | 6 | 4 | 13 |
| Scheduled Receipts | ||||||||||||
| Projected Available Balance | ||||||||||||
| Net Requirements | ||||||||||||
| Planned Order Receipt | ||||||||||||
| Planned Order Release | ||||||||||||
Input Shaft Requirements
| Week: | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| Gross Requirements | ||||||||||||
| Scheduled Receipts | ||||||||||||
| Projected Available Balance | ||||||||||||
| Net Requirements | ||||||||||||
| Planned Order Receipt | ||||||||||||
| Planned Order Release |
Below is the screenshot of formula applied to get the result -

Below is the required table -

Analytics Exercise 9-1 Recently, Phil Harris, the production control manager at Brunswick, read a...
Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine...
Refer to the Excel speadsheet, "Inventory Management," to
complete the "Analytics Exercise: An MRP Explosion - Brunswick
Motors," at the end of Chapter 21 in the textbook. Answer Questions
1-3.
Given Spread Sheet: A-Topic 3 Part 1&2
AND A-Topic 3 Part 3
Please use given information, show formulas/
calculations, and give reasons behind answer.
Part 2 Gear Box Given Information Setu Invento Number of orders (count cells with values for planned order release Set-up Costs=# of Orders X Setup Costs 8...
Do schedule tables for ALL parts.
9. Assume that you are the manager of a shop that assembles power tools. You have just received an order for 50 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components 15 A(2), B(1), C(4 10 E(3,DO) 5 D(2), F(3) 65 E2), D(2) 20 10 30 Saw 2 a. Develop a product structure tree, an assembly time...
There are two (2) Parts to this case. The First part (Part 1) requires you to use the information to:1. Build a Bill of Material (BOM) form the given information2. Determine the Master Production Schedule (MPS) and3. Complete the MRP for all parts including the product. The Second Part (Part 2) will require you to use an indexed BOM to 1. Create the correct MPS from the provided information2. create the MRP for the unit and all of its assemblies/components Part 1:...
Case #2 MGT2315 There are two (2) Parts to this case. The First part (Part 1) requires you to use the information to:1. Build a Bill of Material (BOM) form the given information2. Determine the Master Production Schedule (MPS) and3. Complete the MRP for all parts including the product. The Second Part (Part 2) will require you to use an indexed BOM to 1. Create the correct MPS from the provided information2. create the MRP for the unit and all of...
Question #1 : The product structure tree of a round-top computer desk is given as follows. On-hand inventory information is given in the Table 1 as follows. Level 0 Round-top computer desk (A) Level 1 B(4) C(2) Level 2 E(2) F(3) E(3) D(2) D(1) D(3) Level 3 Table 1: On-hand inventory Item On hand (units) Round-top com r desk 100 48 20 1) Determine number of units of each item required to satisfy a new order of 10 round-top computer...
Audio Products handles the production in the following way. The chassis(radio/CD unit) is assembled in Mexico and has a manufacturing lead time of 3 weeks. The mounting hardware is purchased from a sheet steel company and has a three-week lead time. The finish trim is purchased from a Taiwan electronics company with offices in Los Angeles as prepackaged units consisting of knobs and various trim peices. Trim packages have a two week lead time. Final assembly time may be disregarded...
please answer 14.17
- Data Table for Problems 14.17 through 14.19* Period 1 2 3 4 5 6 7 8 9 10 11 12 requirements 30 40 30 70 20 10 80 50 8 "Holding cost $2.50/unit/week; setup cost $150; lead time 1 week; beginning n Gross inventory 40 m14.17 Develop a lot-for-lot solution and calculate total rel- s evant costs for the data in the table for Problems 14.17 through d 14.19. Px 14.18 Develop an EOQ solution and...
Please help me correct this
question. Thanks
Problem 9-12 One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of...
manufacturing plng/ control
1. Suppose that your company sells a product for which the annual demand is 10,000 units. Holding costs are $1.00 per unit per year, and setup costs are $200 per order (a) What is the economic order quantity for your product? (b) What will be the annual total cost holding and ordering? 2. A company has currently 100 workers. A worker works 40 hours a week, and can at most work 20 hours of overtime per week....