Question

Q4. CPM Consider the following list of activities and predecessors. Activity ProcessorsDuration (days) Build foundation Build

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a)

5 0 E4 8 5

Let Tj be the start time for an activity j

Min Duration

s.t.

TB - TA >= 5
TD - TB >= 8
TC - TB >= 8
TE - TB >= 8
TF - TE >= 4
TG - TF >= 6
TG - TC >= 10

TD + 5 <= Duration
TG + 3 <= Duration

Tj >= 0

(b)

Let Cj be the days crash for an activity-j

Min Z = total crash cost = 30 CA + 15 CB + 20 CC + 40 CD + 20 CE + 30 CF + 40 CG

Subject to,

TB - TA + CA >= 5
TD - TB + CB >= 8
TC - TB + CB >= 8
TE - TB + CB >= 8
TF - TE + CE >= 4
TG - TF + CF >= 6
TG - TC + CC >= 10

CA <= 2, CB <= 3, CC <= 1, CD <= 2, CE <= 2, CF <= 3, CG <= 1

TD + 5 - CD <= 20
TG + 3 - CG <= 20

Tj, Cj >= 0

Add a comment
Know the answer?
Add Answer to:
Q4. CPM Consider the following list of activities and predecessors. Activity ProcessorsDuration (...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Operations Research 4- Consider the (simplified) list of activities and predecessors that are involved in building a house: Description Predecessors Duration (Days) Build foundation Activity Walls...

    Operations Research 4- Consider the (simplified) list of activities and predecessors that are involved in building a house: Description Predecessors Duration (Days) Build foundation Activity Walls and ceilings A Roof Electrical wiring B Put in windows B Put in siding Paint house 10 6 C,F Construct the network for this project, identify the critical path using the (IC,TC,IL,TL, and H) method. 4- Consider the (simplified) list of activities and predecessors that are involved in building a house: Description Predecessors Duration...

  • Activity Predecessors | Duration(days) A B | Description Build foundation Build walls and ceilings Build the...

    Activity Predecessors | Duration(days) A B | Description Build foundation Build walls and ceilings Build the roof Electrical wiring Install windows Put on siding Painting B B Ε CF Ι a) Draw the project diagram, and find the critical path, total duration, and total float and free float for every activity. b) Suppose you are expected to finish the project within 20 days. You find you have to hire more workers in order to shorten the total duration. Please find...

  • I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors...

    I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors Time in Weeks A ---- 2 B A 5 C A 4 D B 3 E C, D 6 F D 3 G F 3 H E, G 4 Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and...

  • 5.) Consider a project whose activities are listed in the table below. Activity A will have...

    5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as…    Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...

  • F: The activities in the following table describe the construction of a new house. Activity Predecessor(s)...

    F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...

  • Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the...

    Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...

  • Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A...

    Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?

  • A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity...

    A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...

  • 8. You have signed a contract to build a garage for the Simpsons. You will receive...

    8. You have signed a contract to build a garage for the Simpsons. You will receive $500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17 working days. Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus...

  • Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...

    Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT