Payback Period = A +B/C
Where,
A = Last period with a negative cumulative cash flow
B = Absolute value of cumulative cash flow at the end of the period A
C = Total cash flow during the period after A
Computation of payback period for project A:
|
Period |
Cash flow |
‘Cumulative cash flow |
|
0 |
($30) |
($30) |
|
1 |
$5 |
($25) |
|
2 |
$10 |
($15) |
|
3 |
$15 |
$0 |
|
4 |
$20 |
$20 |
Payback period for Project A = 2 + $ 15/$15 = 2 + 1 = 3 years
Computation of payback period for project B:
|
Period |
Cash flow |
Cumulative cash flow |
|
0 |
($30) |
($30) |
|
1 |
$20 |
($10) |
|
2 |
$10 |
$0 |
|
3 |
$8 |
$8 |
|
4 |
$6 |
$14 |
Payback period for Project B = 1 + $ 10/$10 = 1 + 1 = 2 years
---------------------------------------------------
Discounted Payback Period = A +B/C
Where,
A = Last period with a discounted negative cumulative cash flow
B = Absolute value of discounted cumulative cash flow at the end of the period A
C = Total discounted cash flow during the period after A
Computation of discounted payback period for Project A:
|
Period |
Cash flow(CA) |
Computation of PV Factor |
PV Factor @ 10 % (F) |
Discounted cash Flow(CA x F) |
Discounted ‘Cumulative cash flow |
|
0 |
($30) |
1/(1+0.1)^0 |
1 |
($30) |
($30) |
|
1 |
$5 |
1/(1+0.1)^1 |
0.909090909090909 |
$4.55 |
($25.45) |
|
2 |
$10 |
1/(1+0.1)^2 |
0.826446280991735 |
$8.26 |
($17.19) |
|
3 |
$15 |
1/(1+0.1)^3 |
0.751314800901578 |
$11.27 |
($5.92) |
|
4 |
$20 |
1/(1+0.1)^4 |
0.683013455365071 |
$13.66 |
$7.74 |
Discounted Payback period for Project A = 3 + $ 5.92/$ 13.66 = 3 + 0.433382 = 3.433382 or 3.43 years
Computation of discounted payback period for Project B:
|
Period |
Cash flow (CB) |
Computation of PV Factor |
PV Factor @ 10 % (F) |
Discounted cash Flow (CB x F) |
Discounted ‘Cumulative cash flow |
|
0 |
($30) |
1/(1+0.1)^0 |
1 |
($30) |
($30) |
|
1 |
$20 |
1/(1+0.1)^1 |
0.909090909090909 |
$18.18 |
($11.82) |
|
2 |
$10 |
1/(1+0.1)^2 |
0.826446280991735 |
$8.26 |
($3.55) |
|
3 |
$8 |
1/(1+0.1)^3 |
0.751314800901578 |
$6.01 |
$2.46 |
|
4 |
$6 |
1/(1+0.1)^4 |
0.683013455365071 |
$4.10 |
$6.55 |
Discounted Payback period for Project B = 2 + $ 3.55/$ 6.01 = 2 + 0.590682 = 2.590682 or 2.59 years
---------------------------------------------------------------------------------
PV factor for period n = 1/ (1+r) n
Where r is rate of interest and n is the number of period
Multiply PV factor with the cash flow of respective year to get discounted cash flow. Discounted Cumulative cash flow in year 0 is the discounted cash flow or initial layout of the project. Add the discounted cash flow of year 1 with discounted cash flow year 0 to get discounted cumulative cash flow in year 1. With this discounted cumulative cash flow of year 1, add discounted cash flow of year 2 and get the discounted cumulative cash flow of year 2 and so on.
Project A Discounted Payback Period:
If excel sheet is like below table, insert formulas as:
|
A |
B |
C |
D |
E |
F |
|
|
1 |
Time period |
0 |
1 |
2 |
3 |
4 |
|
2 |
Cash Flow |
($30) |
$5 |
$10 |
$15 |
$20 |
|
3 |
Disc. Cash Flow |
=B2*(1/(1.1)^0) |
=C2*(1/(1.1)^1) |
=D2*(1/(1.1)^2) |
=E2*(1/(1.1)^3) |
=F2*(1/(1.1)^4) |
|
4 |
Disc. Cum. Cash Flow |
=B3 |
=B4+C3 |
=C4+D3 |
=D4+E3 |
=E4+F3 |
|
5 |
||||||
|
6 |
Discounted payback period A |
=E1 + (-E4/F3) |
This will display as:
|
A |
B |
C |
D |
E |
F |
|
|
1 |
Time period |
0 |
1 |
2 |
3 |
4 |
|
2 |
Cash Flow |
($30) |
$5 |
$10 |
$15 |
$20 |
|
3 |
Disc. Cash Flow |
-30 |
$4.55 |
$8.26 |
$11.27 |
$13.66 |
|
4 |
Disc. Cum. Cash Flow |
-30 |
$(25.45) |
$(17.19) |
$(5.92) |
$7.74 |
|
5 |
||||||
|
6 |
Discounted payback period A |
3.43 |
Calculate payback periods. Please show calculations so I can duplicate it in excel. 7 Your division is considering two projects. Its wACC is 10%, and the projects, after-tax cash flows (in millio...
Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects. Its WACC is 10%, and the projects' after-tax cash flows (in millions of dollars) would be as follows: Expected Cash Flows Time Project A Project B 0 ($30) ($30) 1 $5 $20 2 $10 $10 3 $15 $8 4 $20 $6 a. Calculate the projects' NPVs, IRRs, MIRRs, regular paybacks, and discounted paybacks. WACC = 10% Use Excel's NPV function as explained in NPVA...
can you please show me how to calculate the discounted cash flow? Please dont just give me the answer. g. At a cost of capital of 12%, what is the discounted payback period for these two projects? WACC = 12% Project A Time period 0 1 2 3 4 5 6 7 Cash flow -$375 -$300 -$200 -$100 $600 $600 $926 -$200 Disc. cash flow Disc. cum. cash flow $0 $0 $0 $0 $0 $0 $0 $0 Intermediate calculation for payback Payback...
Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $27 million. You estimate that the cost of capital is 8% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two...
Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $22 million. You estimate that the cost of capital is 12% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two...
6 Instructions Your manager wants you to evaluate two mutually exclusive projects. The cash flows of the project is given in the flowing tables. 8 Project 1 $ uomi Cash flow (30,000) 8,000 10,000 11,000 17,000 12,000 + Onm Project 2 Cash flow $ (15,000) 2,000 5,000 7,000 2,000 25,000 20 The required rate of return is 15%. The first step is too evaluate the project using NPV, IRR, payback rule 21 You will do so in each tab named...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$15,000 $5,000 $5,000 $5,000 $5,000 $5,000 Project N -$45,000 $14,000 $14,000 $14,000 $14,000 $14,000 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M Project N - $12,000 $4,000 $4,000 $4,000 $4,000 $4,000 -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations....
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$21,000 $7,000 $7,000 $7,000 $7,000 $7,000 Project N -$63,000 $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M $(21,000) $7,000 $7,000 $7,000 $7,000 $7,000 Project N $(63,000) $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...