Either of the cost alternatives shown below can be used in a
chemical refining process. If the company’s MARR is 15% per year,
determine which should be selected on the basis of an incremental
ROR analysis.
|
A |
B |
|
|
First cost ,$ |
− 40,000 |
− 61,000 |
|
Annual cost, $/year |
− 25,000 |
− 19,000 |
|
Salvage value, $ |
8,000 |
11,000 |
|
Life, years 5 |
5 |
5 |
|
|
MARR = 15%
Incremental cost (B-A) = 61000 - 40000 = 21000
Annual saving = -19000 + 25000 = 6000
Incremental salvage value = 11000 - 8000 = 3000
t = 5 yrs
Let incremental rate of return be i%, then PW at i% =0
PW = -21000 + 6000*(P/A,i%,5) + 3000*(P/F,i%,5) = 0
6000*(P/A,i%,5) + 3000*(P/F,i%,5) = 21000
dividing by 3000
2*(P/A,i%,5) + (P/F,i%,5) = 7
Using trail and error method
When i = 15%, 2*(P/A,i%,5) + (P/F,i%,5) = 7.20149
When i = 16%, 2*(P/A,i%,5) + (P/F,i%,5) = 7.02470
When i = 17%, 2*(P/A,i%,5) + (P/F,i%,5) = 6.85480
using interpolation
i = 16% + (7.02470-7) / (7.02470-6.85480) *(17-16)
i = 16% + 0.14537
i = 16.15% (Approx) (option D)
As Incremental IRR is greater than MARR, Project B should be selected (option F)
Either of the cost alternatives shown below can be used in a chemical refining process. If the company’s MARR is 15% per year, determine which should be selected on the basis of an incremental ROR ana...
Determine whether either of the alternatives below should be
selected. Use an MARR of 15% per year. Incremental Rate of Return
Analysis must be used. (PLEASE DO NOT USE EXCEL).
First Cost Annual Operating Cost Annual Repair Cost Annual Increase in Repair Cost Salvage Value Life (years) Project A -$60,000 -$15,000 -$5,000 -$1,000 $8,000 15 Project B -$90,000 -$8,000 -$2,000 -$1,500 $12,000 15
5 Questions 4 through 7 are based on the following statement: 1 tually exclusive alternatives, A and B, are to be evaluated by the rate of return (ROR) method. The initial Investment for alternative B is greater than that of alternative A. If the overall ROR of alternative A is less than the MARR and the overall rate of return of alternative B is greater than the MARR, then: A) Alternative B should be compared incrementally to alternative A. B)...
Which alternative of the three alternatives below should be selected if the MARR = 6%? Use the following to compare projects: a. PW analysis b. B/C ratio for each project c. Incremental B/C ratio assessment (define Defender and Challenger in each analysis) d. IRR for each project over its respective service life e. Incremental IRR using the same (a common) number of years for each project Are any of the projects acceptable? Are any not acceptable? Which project would you...
1. Which alternative of the three alternatives below should be selected if the MARR = 6%? Use the following to compare projects: PW analysis B/C ratio for each project Incremental B/C ratio assessment IRR for each project over its respective service life Incremental IRR using the same (a common) number of years for each project Are any of the projects acceptable? Are any not acceptable? Which project would you recommend and why? Alternatives: A B C First Cost $800 $300 ...
Which alternative of the three alternatives below should be
selected if the MARR = 6%? Use the following to compare
projects
a.PW analysis
b.B/C ratio for each project
c.Incremental B/C ratio assessment (Be sure to define Defender
and Challenger in each incremental analysis)
d.IRR for each project over its respective service life
e.Incremental IRR using the same (a common) number of years for
each project
Are any of the projects acceptable? Are any not acceptable? Which project would you recommend...
Consider the four independent alternatives that have 5-year useful life and no salvage value. Alternatives: A B C D Initial Cost (A)$400,000 (B)$100,000 (C)$200,000 (D)$500,000 Uniform Annual Benefit (A)$100,900 (B)$27,700 (C)$46,200 (D)$125,200 ROR (A)8.3% (B)11.9% (C)5% (D)8% Write an equation to determine what alternative to select if MARR is 6%. What is your recommendation if MARR is 10%? And if MARR is 15%?
QUESTION 3For the below ME alternatives, which machine should be selected based on the AW analysis. MARR=10%Machine AMachine BMachine CFirst cost, $26,5383000010000Annual cost, $/year8,0606,0004,000Salvage value, $4,0005,0001,000Life, years362Answer the below questions:A- AW for machine A=QUESTION 4For the below ME alternatives, which machine should be selected based on the AW analysis. MARR=10%Machine AMachine BMachine CFirst cost, $1500021,66710000Annual cost, $/year8,8706,0004,000Salvage value, $4,0005,0001,000Life, years362Answer the below questions:B- AW for machine B=
Question 13 15 points Save Answer The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabi. Determine which one should be selected based on a B/C analysis. Assume an interest rate of 10% per year and a 5-year study period. Alternative X Alternative Y First costs, AED 40,000 90,000 20,000 Annual M&O costs, AED per year 50,000 150,000 Benefits, AED per year 120,000 Disbenefits, AED per year 30,000 10,000 Match the closest correct...
Question 13 15 points Save Answer The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabi. Determine which one should be selected based on a B/C analysis. Assume an interest rate of 10% per year and a 5 year study period Alternative X Alternative Y 90,000 First costs, AED 40.000 50,000 20,000 Annual M&O costs, AED per year Benefits, AED per year 120,000 150,000 Disbenefits, AED per year 30,000 10,000 Match the closest...
Question 13 15 points Save Answer The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabi. Determine which one should be selected based on a B/C analysis. Assume an interest rate of 10% per year and a 5 year study period Alternative X Alternative Y 90,000 First costs, AED 40.000 50,000 20,000 Annual M&O costs, AED per year Benefits, AED per year 120,000 150,000 Disbenefits, AED per year 30,000 10,000 Match the closest...