Let IRR be i%
PW at IRR is 0
PW = -25000000 + (7500000 - 2750000) *(P/A, i%,10) + 1500000 * (P/F, i%,10) = 0
-25000000 + 4750000 *(P/A, i%,10) + 1500000 * (P/F, i%,10) = 0
4750000 *(P/A, i%,10) + 1500000 * (P/F, i%,10) = 25000000
dividing by 50000
95 *(P/A, i%,10) + 30 * (P/F, i%,10) = 500
using trail and error method
when i = 14%, value of 95 *(P/A, i%,10) + 30 * (P/F, i%,10) = 95 * 5.216116 + 30 * 0.269744 = 503.623301
when i = 15%, value of 95 *(P/A, i%,10) + 30 * (P/F, i%,10) = 95 * 5.018769 + 30 * 0.247185 = 484.198561
using interpolation
i = 14% + (503.623301 - 500) / (503.623301 - 484.198561) *(15%-14%)
i = 14% + 0.18653%
i = 14.186% = 14.19% (Approx)
As IRR is greater than 10%, this project is acceptable
0.7. A large automobile manufacturer is considering the installation of a high-tech material handling system for $25...