1
| Project | |||||||||
| Discount rate | 0.08 | ||||||||
| Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Cash flow stream | -7700 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 |
| Discounting factor | 1 | 1.08 | 1.1664 | 1.259712 | 1.360489 | 1.469328 | 1.586874 | 1.713824 | 1.85093 |
| Discounted cash flows project | -7700 | 1787.037 | 1654.664 | 1532.096 | 1418.6076 | 1313.526 | 1216.227 | 1126.136 | 1042.719 |
| NPV = Sum of discounted cash flows | |||||||||
| NPV Project = | 3391.01 | ||||||||
| Where | |||||||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||||||
| Discounted Cashflow= | Cash flow stream/discounting factor | ||||||||
2
| Project | |||||||||
| Discount rate | 0.24 | ||||||||
| Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Cash flow stream | -7700 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 |
| Discounting factor | 1 | 1.24 | 1.5376 | 1.906624 | 2.3642138 | 2.931625 | 3.635215 | 4.507667 | 5.589507 |
| Discounted cash flows project | -7700 | 1556.452 | 1255.203 | 1012.26 | 816.33904 | 658.3379 | 530.9177 | 428.1594 | 345.2899 |
| NPV = Sum of discounted cash flows | |||||||||
| NPV Project = | -1097.04 | ||||||||
| Where | |||||||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||||||
| Discounted Cashflow= | Cash flow stream/discounting factor | ||||||||
3
| Project | |||||||||
| IRR is the rate at which NPV =0 | |||||||||
| IRR | 0.187085395 | ||||||||
| Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Cash flow stream | -7700 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 | 1930 |
| Discounting factor | 1 | 1.187085 | 1.409172 | 1.672807 | 1.985765 | 2.357273 | 2.798284 | 3.321802 | 3.943263 |
| Discounted cash flows project | -7700 | 1625.831 | 1369.599 | 1153.749 | 971.91763 | 818.7428 | 689.7084 | 581.01 | 489.4424 |
| NPV = Sum of discounted cash flows | |||||||||
| NPV Project = | 0.000162736 | ||||||||
| Where | |||||||||
| Discounting factor = | (1 + IRR)^(Corresponding period in years) | ||||||||
| Discounted Cashflow= | Cash flow stream/discounting factor | ||||||||
| IRR= | 18.71% | ||||||||
6. walx 4.00 points hat provides anush os 1 3cs 5770 oday Requirement 1: t, what is the NPV of the p calculations. Roun...
A project that provides annual cash flows of $1,930 for 8 years costs $7,700 today. Requirement 1: At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).) NPV $ Requirement 2: At a required return of 24 percent, what is the NPV of the project? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Round your...
A project that provides annual cash flows of $2,650 for nine years costs $10,900 today. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. a. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to...
7 A project that provides annual cash flows of $2,620 for eight years costs $9,430 today a. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What is the NPV for the project if the required return is 7 percent? (Do not round intermediate calculations. Round your answer to 2 decimal places, e.g., 32.16.) NPV At a required return of 7 percent, should the firm accept this project? O Accept O Reject What is the NPV for the project if the required return is 19 percent? (Negative amount should be indicated...
A project that will provde annual cash flows of $2,750 for nine years costs $9.000 today, a. At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 29 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A project that will provde annual cash flows of $2,550 for nine years costs $10,500 today. a. At a required return of 11 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 27 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A project that will provde annual cash flows of $3,000 for nine years costs $10,000 today. a. At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 28 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A project that will provde annual cash flows of $2,750 for nine years costs $9,000 today. a. At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 29 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
newconnect.mheducation.com Cash Flow - Part 2 Chapter 5 - DCF & Interest Rates - Part 3 Chapter 8 PV & Investment Criteria i Saved A project that will provde annual cash flows of $2,350 for nine years costs $9,700 today, a. At a required return of 12 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g. 32.16.) b. At a required return of 28 percent, what is...