Question

3) A product has an average labor cost of $10/hr. The overhead expenses are 100% of labor cost. Time for the first unit-10 ho
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1)

We know that normal form of learning curve is given by

Yx=Kxn

Where

K=Direct labor hours needed for first unit=10 hours

x=unit number=4

Yx= labor hours needed for xth unit i.e. 4th unit=8.1 hours

n=log10b/log102 and b=learning percentage

We can estimate the value of n with the help of given equation

Yx=Kxn

8.1=10*4n

0.81=4n

Taking natural log both sides

ln(0.81)=nln(4)

n=ln(0.81)/ln(4)=-0.152

Now we can find the value of b

n=log10b/log102

-0.152=log10b/0.301030

log10b=-0.152*0.301030=-0.04576

b=10-0.04576=0.90

So, Learning percentage=90%

b)

Let us find the time required for 500th unit

Yx=Kxn

Y500=10*(500)-0.152=3.888 minute

Labor Cost=3.888*10=$38.88

Overhead =10% of labor cost=38.88*10%=$3.89

Add a comment
Know the answer?
Add Answer to:
3) A product has an average labor cost of $10/hr. The overhead expenses are 100% of labor cost. Time for the first...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Part IV-Problems (55 points) A. Highestec, Inc is beginning the production of a new product. Management...

    Part IV-Problems (55 points) A. Highestec, Inc is beginning the production of a new product. Management believes that 500 labor hours will be required to complete the new unit. A 90 percent cumulative average-time learning curve model for direct labor hours is assumed to be valid. Data on costs are as follows: S50,000 per unit s20 per direct labor hour $30 per direct labor hour Direct materials Direct labor Variable manufacturing overhead Required: a. Set up a table with columns...

  • Data for a new product that is very labor intensive introduced by Hicks Brothers in the...

    Data for a new product that is very labor intensive introduced by Hicks Brothers in the operation in Hendersonville, TN is given below. The average labor cost including overhead expenses is about $20 per hour. Time for the very first unit = 9 hours Time for the second unit = 8.462 hours. What is the labor cost for the 1000-th unit ? A. $62.30 B. $55.85 C. 69.94 D. $75.23

  • 10 Points What is the labor-hour estimate for a 95% learning curve unit #16, if the...

    10 Points What is the labor-hour estimate for a 95% learning curve unit #16, if the first unit is 100 man- hours? a. 95 labor-hours b. 80.45 labor-hours 90.25 labor-hours d. None of the above c.

  • World Defense manufactures radar systems. It has just completed the manufacture of its first newly designed...

    World Defense manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: (Click icon to view data) Requirement Calculate the total variable costs of producing 2, 4, and 8 units. Begin by calculating the total cumulative time in labor-hours. (Round the cumulative average time per unit to the nearest whole number.) Cumulative average time Number of Cumulative total time: units per unit: Labor-hours Labor-hours 3,145 6,290 2 2,673...

  • 3) Assume that the first unit of production required 3 hours time for assembly. The learning...

    3) Assume that the first unit of production required 3 hours time for assembly. The learning curve rate is 75%. Find the time needed to assemble the first 6 units?

  • 39. Budgeting for Sales, Production, Direct Materials, Direct Labor, and Manufacturing Overhead. ...

    NEED ANSWER OF THE " F " PART ONLY! 39. Budgeting for Sales, Production, Direct Materials, Direct Labor, and Manufacturing Overhead. Sports Bars Inc., produces energy bars and sells them by the case (1 unit - 1 case). Information to be used for the operating budget this coming year follows: Average sales price for each case is estimated to be $25. Unit sales for this coming year, ending December 31, are expected to be as follows First quarter 80,ooo Second...

  • Problem 3-56 Predetermined Overhead Rate; Different Time Periods; Pricing (LO 4) [The following information applies to...

    Problem 3-56 Predetermined Overhead Rate; Different Time Periods; Pricing (LO 4) [The following information applies to the questions displayed below.] Rochester Heating Systems, Inc. calculates its predetermined overhead rate on a quarterly basis. The following estimates were made for the current year Quarterly Predetermined Overhead Rate (per Estimated Manufacturing Direct-Labor direct-labor Hours 25,000 Estimated Overhead hour) First quarter $100,000 Second 96,000 16,000 12,500 14,000 quarter Third quarter 37,500 Fourth 70,000 quarter Total $303,500 67,500 The firm's main product, part number...

  • UNTER COMPONENTS Star 150 150 Costs per unit Direct materials Direct labor Variable overhead Fixed overhead...

    UNTER COMPONENTS Star 150 150 Costs per unit Direct materials Direct labor Variable overhead Fixed overhead Total cost per unit Price Units sold Star 100 130 $ 60 30 180 400 $ 580 $ 4,000 40 240 510 780 2,000 40 Additional Information: Variable overhead varies with quantity of direct labor-hours. Average wage rate per hour Plant capacity (in direct labor-hours) 20,000 Current production (in direct labor-hours) 10,000 Requirement a. Information: Star 100 2,500 400 $ Star 150 2,500 500...

  • Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor...

    Ontario, Inc. manufactures two products, Standard and Enhanced, and applies overhead on the basis of direct-labor hours. Anticipated overhead and direct-labor time for the upcoming accounting period are $800,000 and 25,000 hours, respectively. Information about the company’s products follows. Standard: Est. production volume, 3000 units    Direct-material cost, $25 per Unit    Direct Labor per unit, 3 hrs at $12 per hr Enhanced: Est. production volume, 4000 units    Direct material cost, $40 per Unit    Direct Labor per unit,...

  • Sedona Company set the following standard costs for one unit of its product for 2017. Direct material (20 Ibs. $2.10 per Ib.) Direct labor (10 hrs. $8.80 per hr.1) Factory variable overhead (10...

    Sedona Company set the following standard costs for one unit of its product for 2017. Direct material (20 Ibs. $2.10 per Ib.) Direct labor (10 hrs. $8.80 per hr.1) Factory variable overhead (10 hrs. $4.00 per hr. Factory tixed overhead (10 hr. $1.80 per hr.) Standard cost s 42.00 88.00 40.00 18.00 $188.00 The $5.80 ($4.00+$1.80) total overhead rate per direct labor hour is based on an expected operating level equal to 70% of the factory's capacity of 70,000 units...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT