Question

Given the following four projects and their cash flows, calculate the discounted payback period with a 5% discount rate...

  1. Given the following four projects and their cash flows, calculate the discounted payback period with a 5% discount rate discount rate.

Cash Flow

A

B

C

D

Cost

$     10,000

$    25,000

$   45,000

$        100,000

Cash flow year 1

$      4,000

$      2,000

$   10,000

$          40,000

Cash flow year 2

$      4,000

$      8,000

$   15,000

$          30,000

Cash flow year 3

$      4,000

$    14,000

$   20,000

$          20,000

Cash flow year 4

$      4,000

$    20,000

$   20,000

$          10,000

Cash flow year 5

$      4,000

$    26,000

$   15,000

$                  -

Cash flow year 6

$      4,000

$    32,000

$   10,000

$                   -  

PLEASE SHOW ME ALL THE STEPS, I'M TRYING TO LEARN THE BASICS OF IT. THANK YOU!

0 0
Add a comment Improve this question Transcribed image text
Answer #1
A Discount rate= 0.05
Year Cash flow stream Cumulative cash flow Discounting factor Discounted CF Cumulative cash flow Cumulative discounted CF
0 -10000 -10000 1 -10000 -10000 -10000
1 4000 -6000 1.05 3809.524 -6000 -6190.48
2 4000 -2000 1.1025 3628.118 -2000 -2562.36
3 4000 2000 1.157625 3455.35 2000 892.9921
4 4000 6000 1.215506 3290.81 6000 4183.802
5 4000 10000 1.276282 3134.105 10000 7317.907
6 4000 14000 1.340096 2984.862 14000 10302.77
Discounted payback period is the time by which discounted cashflow cover the intial investment outlay
this is happening between year 2 and 3
therefore by interpolation payback period = 2 + (0-(-2562.36))/(892.99-(-2562.36))
2.74 Years
Where
Discounting factor =(1 + discount rate)^(corresponding year)
Discounted Cashflow=Cash flow stream/discounting factor
B Discount rate= 0.05
Year Cash flow stream Cumulative cash flow Discounting factor Discounted CF Cumulative cash flow Cumulative discounted CF
0 -25000 -25000 1 -25000 -25000 -25000
1 2000 -23000 1.05 1904.762 -23000 -23095.2
2 8000 -15000 1.1025 7256.236 -15000 -15839
3 14000 -1000 1.157625 12093.73 -1000 -3745.28
4 20000 19000 1.215506 16454.05 19000 12708.77
5 26000 45000 1.276282 20371.68 45000 33080.45
6 32000 77000 1.340096 23878.89 77000 56959.35
Discounted payback period is the time by which discounted cashflow cover the intial investment outlay
this is happening between year 3 and 4
therefore by interpolation payback period = 3 + (0-(-3745.28))/(12708.77-(-3745.28))
3.23 Years
Where
Discounting factor =(1 + discount rate)^(corresponding year)
Discounted Cashflow=Cash flow stream/discounting factor
C Discount rate= 0.05
Year Cash flow stream Cumulative cash flow Discounting factor Discounted CF Cumulative cash flow Cumulative discounted CF
0 -45000 -45000 1 -45000 -45000 -45000
1 10000 -35000 1.05 9523.81 -35000 -35476.2
2 15000 -20000 1.1025 13605.44 -20000 -21870.7
3 20000 0 1.157625 17276.75 0 -4594
4 20000 20000 1.215506 16454.05 20000 11860.05
5 15000 35000 1.276282 11752.89 35000 23612.95
6 10000 45000 1.340096 7462.154 45000 31075.1
Discounted payback period is the time by which discounted cashflow cover the intial investment outlay
this is happening between year 3 and 4
therefore by interpolation payback period = 3 + (0-(-4594))/(11860.05-(-4594))
3.28 Years
Where
Discounting factor =(1 + discount rate)^(corresponding year)
Discounted Cashflow=Cash flow stream/discounting factor
A Discount rate= 0.05
Year Cash flow stream Cumulative cash flow Discounting factor Discounted CF Cumulative cash flow Cumulative discounted CF
0 -100000 -100000 1 -100000 -100000 -100000
1 40000 -60000 1.05 38095.24 -60000 -61904.8
2 30000 -30000 1.1025 27210.88 -30000 -34693.9
3 20000 -10000 1.157625 17276.75 -10000 -17417.1
4 10000 0 1.215506 8227.025 0 -9190.1
Discounted payback period is the time by which discounted cashflow cover the intial investment outlay
This is not happening during project life hence it cannot be calculated
Where
Discounting factor =(1 + discount rate)^(corresponding year)
Discounted Cashflow=Cash flow stream/discounting factor
Add a comment
Know the answer?
Add Answer to:
Given the following four projects and their cash flows, calculate the discounted payback period with a 5% discount rate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Discounted payback period) Assuming an appropriate discount rate of 11 percent, what is the discounted payback...

    Discounted payback period) Assuming an appropriate discount rate of 11 percent, what is the discounted payback period on a project with an initial outlay of $100,000 and the following cash flows? Year 1 $30,000 Year 2 $35,000 Year 3 $25,000 Year 4 $25,000 Year 5 $30,000 Year 6 $20,000 The project's discounted payback period is years. (Round to two decimal places.)

  • 6 Instructions Your manager wants you to evaluate two mutually exclusive projects. The cash flows of...

    6 Instructions Your manager wants you to evaluate two mutually exclusive projects. The cash flows of the project is given in the flowing tables. 8 Project 1 $ uomi Cash flow (30,000) 8,000 10,000 11,000 17,000 12,000 + Onm Project 2 Cash flow $ (15,000) 2,000 5,000 7,000 2,000 25,000 20 The required rate of return is 15%. The first step is too evaluate the project using NPV, IRR, payback rule 21 You will do so in each tab named...

  • (Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year...

    (Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Project A Project B Year Cash Flow...

  • Discounted payback period. Becker, Inc. uses the discounted payback period for projects costing less than $25,000 and h...

    Discounted payback period. Becker, Inc. uses the discounted payback period for projects costing less than $25,000 and has a cutoff period of four years for these small-value projects. Two projects, R and S, in the following table, PE, are under consideration. Their anticipated cash flows are listed in the following table. If Becker uses a discount rate of 4% on these projects, are they accepted or rejected? If it uses a discount rate of 8%? A discount rate of 18%?...

  • Discounted payback period. Becker, Inc. uses the discounted payback period for projects costing less than $25,000...

    Discounted payback period. Becker, Inc. uses the discounted payback period for projects costing less than $25,000 and has a cutoff period of four years for these small-value projects. Two projects, R and S, in the following table, B are under consideration. Their anticipated cash flows are listed in the following table. If Becker uses a discount rate of 6% on these projects, are they accepted or rejected? If it uses a discount rate of 12%? A discount rate of 18%?...

  • QUESTION 1 Star Industries is considering three alternative projects for the company's investment. The cash flows for three independent projects are as follows: Year 1 Project A ($50,000) $10,...

    QUESTION 1 Star Industries is considering three alternative projects for the company's investment. The cash flows for three independent projects are as follows: Year 1 Project A ($50,000) $10,000 $15,000 $20,000 $25,000 $30,000 Project B ($100,000) $25,000 $25,000 $25,000 $25,000 $25,000 Project C ($450,000) $200,000 $200,000 $200,000 a) If the discount rate for all three projects is 9.5 percent, calculate the profitability index (PI) of these three projects. Which project will be accepted if the projects are mutually exclusive? b)...

  • project's appropriate discount rate is 12 percent, what is the proces discounted payback period (Discounted Payback...

    project's appropriate discount rate is 12 percent, what is the proces discounted payback period (Discounted Payback periodies Restaurants is considering project with the following expected cash flows The projects discounted payback period is yours (Round to be decimal places) 1 Data Table PROJECT CASH FLOW - $20 million 80 milion 65 milion 80 millon 95 m. (Click on the concated on the h ome of the data above in order to conten t Print Done

  • What is the DISCOUNTED PAYBACK PERIOD for the following project? Discount Rate 6.00% Investment $15,000.00 Cash...

    What is the DISCOUNTED PAYBACK PERIOD for the following project? Discount Rate 6.00% Investment $15,000.00 Cash Flow Year 1 $3,000.00 Cash Flow Year 2 $4,000.00 Cash Flow Year 3 $5,000.00 Cash Flow Year 4 $6,000.00

  • Question 5 a.   Given the following cash flows, for the two independent projects A and B,...

    Question 5 a.   Given the following cash flows, for the two independent projects A and B, calculate i.   Payback Period    ii.   Accounting rate of return    iii.   Net Present Value iv.   Profitability index And recommend acceptance or rejection of projects considering individual techniques of capital budgeting. A rate of 10 % has been selected for the NPV analysis.     Project A   Project B Initial outlay   $50,000   $100,000 Cash inflows         Year 1   $10,000   $ 25,000 Year 2   15,000  ...

  • What is the estimated payback period of a project whose cost is $90,000 and benefits estimated...

    What is the estimated payback period of a project whose cost is $90,000 and benefits estimated to be $30,000 in each of the next five years? _________________ years If the cumulative net inflow for a project is ($500), and in the next year, inflows total $800 and outflows total $100, what is the cumulative net inflow at the end of the next year? Assuming a 10 percent discount rate, calculate the net present value (NPV) of the following cash flows...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT