Solution:
1 a.)
Predetermined overhead rate
| Choose numerator | / | Choose denominator | = | Predetermined overhead rate |
| Estimated overhead costs | / | Estimated direct labor costs | = | Predetermined overhead rate |
| 1,300,000 | / | $20,000,000 | = | 65% |
* Estimated direct labor costs
=40 persons × 2500 hrs.× $20
= $2,000,000
1b.)
| Job no. | Direct labor (in $) | Overhead costs applied (in $) |
| 201 | 605,000 | 393,250 (605000 × 65%) |
| 202 | 564,000 | 366,600 (564000 ×65%) |
| 203 | 299,000 | 194,350 (299,000 × 65%) |
| 204 | 717,000 | 466,050 (717,000 × 65%) |
| 205 | 315,000 | 204,750 (315000 × 65%) |
| 206 | 18,000 | 11700 (18,000 × 65%) |
| Total | 2,518,000 | 1,636,700 |
* Overhead cost applied =Direct labor × Predetermined overhead rate
1c.)
Factory overhead
| Actual overhead costs | $1,665,000 | $1,636,700 | Applied overhead costs |
| Under applied overhead | $28,300 |
2.) Journal entry
| No. of event | Date | General Journal | Debit | Credit |
| 1. | Dec.31 | Cost of goods sold | $28,300 | |
| Factory overhead | $28,300 | |||
| (To record the cost of goods sold) |
Req 1A Req 1B Req 1C Req 2 Assuming that any over- or underapplied overhead is not material, prepare...
In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons working an average of 3,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 336,200 276,000 157,000 105,000 85,000 625,000 77,000 85,800...
1 In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 50 persons working an average of 2,500 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 333,200 128,000 154,000 102,000 82,000 494,000 74,000...
Check Problem 15-4A Overhead allocation and adjustment using a predetermined overhead rate LO P3, P4 In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons working an average of 2,000 hours each at an average wage rate of $30 per hour. The manager also estimated the following manufacturing overhead costs for 2017 0 Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used...
In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons working an average of 3,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor $ 316, 200 Factory supervision 188,800 Rent on factory building 147,000 Factory utilities 95,000 Factory insurance expired 75, eee Depreciation-Factory equipment 521,000 Repairs expense-Factory equipment 67,000 Factory supplies used 75,800 Miscellaneous production costs 43,000 Total...
In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 55 persons working an average of 2.000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 261,200 156,000 152, eee 1ee, eee se, eee...
In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons working an average of 2,000 hours each at an average wage rate of $30 per hour. The manager also estimated the following manufacturing overhead costs for 2017. Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Pactory supplies used Miscellaneous production costs Total estimated overhead coats $ 332,200 243,000 103,000 101,000 81,000 496,000 73,000 81,800...
In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 50 persons working an average of 2,000 hours each at an average wage rate of $25 per hour. The manager also estimated the following manufacturing overhead costs for 2017. Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 319,200 240,000 140,000 88,000 68,000 480,000 60,000 68,800...
At the beginning of the year, Learer Company’s manager estimated
total direct labor cost assuming 40 persons working an average of
2,000 hours each at an average wage rate of $40 per hour. The
manager also estimated the following manufacturing overhead costs
for the year.
Indirect labor
$
324,200
Factory supervision
355,000
Rent on factory building
145,000
Factory utilities
93,000
Factory insurance expired
73,000
Depreciation—Factory equipment
750,000
Repairs expense—Factory equipment
65,000
Factory supplies used
73,800
Miscellaneous production costs
41,000
Total...
Number 5 please finish all of them.
5 Problem 02-4A Overhead allocation and adjustment using a predetermined overhead rate LO P3, P4 At the beginning of the year, Learer Company's manager estimated total direct labor cost assuming 50 persons working an average of 2,000 hours each at an average wage rate of $25 per hour. The manager also estimated the following manufacturing overhead costs for the year. 1 points еВook Indirect labor $ 319,200 240,000 140,000 88,000 68,000 Factory supervision...
At the beginning of the year, Learer Company's manager estimated total direct labor cost assuming 35 persons working an average of 3,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for the year. Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 335,200 165,000 156,000 104,000 84,000 413,000...