NPW of suspension bridge = -600m - 120m - 2.5m *(P/A, 8%,50) - 0.4m *(P/G, 8%,50) - 190m *(P/F, 8%,25) - 25m *(P/F, 8%,50)
= -600m - 120m - 2.5m *12.233485 - 0.4m * 139.592790 - 190m * 0.146018 - 25m * 0.021321
= -834.70 m
NPW of cantilever bridge = -550m - 100m - 3m *(P/A, 8%,50) - 0.3m *(P/G, 8%,50) - 210m *(P/F, 8%,25) - 30m *(P/F, 8%,50)
= -550m - 100m - 3m *12.233485 - 0.3m * 139.592790 - 210m * 0.146018 - 30m * 0.021321
= -759.88 m
As the Present cost of cantilever system is less, it should be selected
BOY 1) The Department of Transportation of a Municipality is planning to construct an additional bridge to speed up eva...
1) The Department Of Transportation of a Municipality is planning to construct an additional bridge to speed up evacuation in case of an emergency. Two sol utions are considered, both with a 50 years life span: Cantilever Suspension Bridge Bridge 550 600 Construction Cost 100 Land Acquisition 120 3 2.5 Annual 0&M 0.3 0.4 Annual 0&M increase 210 Major Maintenance (at 25 yrs) Decommissioning cost 190 30 25 (NOTE: all costs are in Million $) The Department uses an interest...
In order to improve evacuation routes out of New Orleans in the event of another major disaster such as Hurricane Katrina, the Louisiana Department of Transportation (L-DoT) is planning to construct an additional bridge across the Mississippi River. The department uses an interest rate of 8% and plans a 50-year life for either bridge. Which design has the better present worth? All costs in $M Land acquisition Annual O & M Annual increase Major Maintenance (Year 25 Salvage Cost nitial...