Xia Corporation is a company whose sole assets are $ 100, 000 in cash and three projects that it will undertake. The projects are risk-free and have the following cash flows:
Project Cash Flow Today Cash Flow in One Year
A -$ 21,000 $ 27,000
B -$15,000 $30,000
C -$ 56,000 $ 82,000
Xia plans to invest any unused cash today at the risk-free interest rate of 10.6 %. In one year, all cash will be paid to investors and the company will be shut down. a. What is the NPV of each project? Which projects should Xia undertake and how much cash should it retain? b. What is the total value of Xia's assets (projects and cash) today? c. What cash flows will the investors in Xia receive? Based on these cash flows, what is the value of Xia today? d. Suppose Xia pays any unused cash to investors today, rather than investing it. What are the cash flows to investors in this case? Based on these cash flows, what is the value of Xia today? e. Explain the relationship in your answers to parts (b), (c), and (d).
a). Project NPVs: Since the projects are risk-free, the discount rate will be the risk-free interest rate of 10.6%
| Project | CF0 | CF1 | PV of
CF1 CF1/(1+10.6%) |
NPV (CF0 + PV of CF1) |
| A | (21,000.00) | 27,000.00 | 24,412.30 | 3,412.30 |
| B | (15,000.00) | 30,000.00 | 27,124.77 | 12,124.77 |
| C | (56,000.00) | 82,000.00 | 74,141.05 | 18,141.05 |
Total investment required in the three projects = 21,000 + 15,000 + 56,000 = 92,000
Since the company has 100,000 in cash, it can invest in all three projects (all three have positive NPVs). Retained cash will then be 100,000 - 92,000 = 8,000
b). Total value of Xia today = total cash + project NPVs
= 100,000 + 3,412.30 + 12,124.77 + 18,141.05 = 133,678.12
c). After 1 year, investors will receive the cash flows from the projects and the total amount of retained cash invested at 10.6% for a year
= 27,000 + 30,000 + 82,000 + (8,000*(1+10.6%)) = 139,000 + 8,848 = 147,848
Based on the cash flow of 147,848 after 1 year, the value of the company today is the present value of 147,848 which is
147,848/(1+10.6%) = 133,678.12
d). If investors receive the retained cash today and the cash flows from the projects after 1 year then the cash flows will be:
Cash flow today (CF0) = 8,000
Cash flow after 1 year (CF1) = 27,000 + 30,000 + 82,000 = 139,000
Value of the company today = 8,000 + 139,000/(1+10.6%) = 8,000 + 125,678.12 = 133,678.12
e). The answers for parts b,c and d are the same. This is so because the timing of the cash flows is irrelevant. The value of the company will always be the sum of the present value of all future cash flows. If the company pays retained cash (8,000) to its investors today then they can obtain the same amount by investing it at 10.6% for a year (8,848). Similarly, they can borrow 8,000 today against the expected future cash flow of 8,848.
Xia Corporation is a company whose sole assets are $ 100, 000 in cash and three projects that it will undertake. The pro...
Can) ou are in the process of purchasing a new automobile that will cost you $27,500. The dealership is offering you either a $2,500 rebate (applied toward the purchase price) or financing at a 0.9% APR for 48 months (with payments made at the end of the month) and no rebate. You have been pre-approved for an auto loan through your local credit union at an interest rate of 5.5% APR for 48 months. If you take the $2,500 rebate...
Your firm has identified three potential investment projects. The projects and their cash flows are shown here: Cash Flow Today (millions) $7 $7 $18 Cash Flow in One Year (millions) $23 $3 -$8 Project Suppose all cash flows are certain and the risk-free interest rate is 11%. a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c. If the firm can choose any two of these...
Your firm has identified three potential investment projects. The projects and their cash flows are shown below: Project Cash Flow Today (millions) Cash Flow in One Year (millions) A -$7 $15 B $7 $4 C $19 -$6 Suppose all cash flows are certain and the risk-free interest rate is 9%. (a) The NPV of Project A is $Answermillion. (Round to two decimal places.) (b) The NPV of Project B is $Answermillion. (Round to two decimal places.) (c) The...
Your firm has identified three potential investment projects. The projects and their cash flows are shown here: (Click on the icon located on the top-right corner of the data table below in order to copy its contents into a spreadsheet.) Project Cash Flow Today (millions) Cash Flow in One Year (millions) A -$15 $$16 B $4 $3 C $17 −$11 Suppose all cash flows are certain and the risk-free interest rate is 6%. a. What is the NPV of each...
U2 - 6
?(Round to two decimal? places.)
Your firm has identified three potential investment projects. The projects and their cash flows are shown here: Cash Flow Today (millions) -$14 $4 S22 Cash Flow in One Year (millions) 523 $4 - $7 Project Suppose all cash flows are certain and the risk-free interest rate is 9% a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c....
(1)Your firm has identified three potential investment projects. The projects and their cash flows are shown here (Project Cash Flow Today ($) Cash Flow in One Year ($)) A -10- 20 B 5 -5 C 20 -10 Suppose all cash flows are certain and the risk-free interest rate is 10%. a. What is the NPV of each project? b. If the firm can choose only one of these projects, which should it choose? c. If the firm can choose any...
Consider a project with free cash flows in one year of $133,605 in a weak market or $196,786 in a strong market, with each outcome being equally likely. The initial investment required for the project is $65,000, and the project's unlevered cost of capital is 24%. The risk-free interest rate is 9%. (Assume no taxes or distress costs.) a. What is the NPV of this project? The NPV is $ _____? b. Suppose that to raise the funds for the...
Consider a project with free cash flows in one year of $132,459 in a weak market or $193,776 in a strong market, with each outcome being equally likely. The initial investment required for the project is $60,000, and the project's unlevered cost of capital is 22%. The risk-free interest rate is 3%. (Assume no taxes or distress costs.) a. What is the NPV of this project? b. Suppose that to raise the funds for the initial investment, the project is...
Q1. Inatech is contemplating two different projects and decides to perform a financial analysis to determine which is more financially lucrative. Project A and B have the cash flows as shown and Inatech uses a required rate of return of 10% and an inflation rate of 4%. Compute the payback in years and the net present value for both projects and offer advice as to the best course of action. (4 marks) Yearl A B 0 -$100.000|-$400,000 $20,000 $75,000 2....
(b) A company is evaluating between two mutually exclusive projects. The required initial investments and the expected net cash flows from the projects are as follows: Project 1 Project 2 0 -$4,000,000 - $4,000,000 1 $1,900,000 $1,100,000 2 $2,255,000 $1,900,000 3 $2,000,000 $2,000,000 The company accepts any project for which the payback period is within 3 years, Which of these projects should be chosen using the payback period as the capital budgeting measure? (3 marks) An Australian multinational company is...