First let us work out the variable cost by using high low method
It will be calculated as highest cost activity - lowest cost activity / highest cost unit - lowest cost unit
So ($5490- $4500)/ (6600-4900) I.e . 990/ 1700 which is 0.5824 per unit
Now fixed cost is calculated as highest activity cost - (variable cost per unit * highest activity units)
So 5490 - (0.5824*6600) I.e. 5490- 3484 which is 1646
Total cost is calculated as fixed cost + variable cost
Hence the correct option is Y= $1646 + 0.5824x
Denver Manufacturing Denver Manufacturing would like to do a better job budgeting for maintenance costs and, conseq...
Denver Manufacturing Denver Manufacturing would like to do a better job budgeting for maintenance costs and, consequently, they have prepared a schedule showing maintenance costs and units produced for the past five months as follows: Lanuary Februar Number of units produced 5,400 6,600 4,900 5,600 6,000 Total maintenance costs $4,800 5,180 4,500 4.900 5,490 March April May Refer to the Denver Manufacturing information above. Using the high/low method, if Denver expects to produce 4,830 units in June, what will be...