
We need to caculate the exact NPV and IRR for both the projects in order to know the comparison.
[We can find the same through graphs also]
Through Graph
For NPV [Find Points where Cost of capital = 14%
For IRR [Find point where NPV = 0]
Now calculating via excel
| Discount Rate/WACC (r) | 14% | ||||
| PROJECT W | |||||
| years | 0 | 1 | 2 | 3 | 4 |
| Cash-Outflows | 1,000 | ||||
| Cash-Inflows | 200 | 350 | 400 | 600 | |
| Net Cashflows (Inflow - Outflow) | -1,000 | 200 | 350 | 400 | 600 |
| Discounted
Cashflow = Net CF / (1+r)^years |
-1,000 | 175 | 269 | 270 | 355 |
| NPV = sum of all discounted CF | 69.99 | ||||
| IRR = IRR (net CF) | 16.852% | ||||
| PROJECT X | |||||
| years | 0 | 1 | 2 | 3 | 4 |
| Cash-Outflows | 1,500 | ||||
| Cash-Inflows | 350 | 500 | 600 | 750 | |
| Net Cashflows (Inflow - Outflow) | -1,500 | 350 | 500 | 600 | 750 |
| Discounted
Cashflow = Net CF / (1+r)^years |
-1,500 | 307 | 385 | 405 | 444 |
| NPV = sum of all discounted CF | 40.79 | ||||
| IRR = IRR (net CF) | 15.167% |
Hence, we can see
NPV (Project W) > NPV (Project X), implies Project W is better than Project X
and IRR (Project W) > IRR (Project X).. both have IRR > WACC and hence both rae favourable, But Project W > Project X
Hence both methods AGREE.
s. Understanding the NPV profile Aa Aa If an independent project with conventional, or normal, cash flows is being...
If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 0 -$1,00 Year Project W -$1,000 1 $200 2 $350 $400 $600 Project x -$1,500 $350 $500 $600 $750 Project X Project W If the weighted average cost of capital (WACC) for each...
If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars Year Project Y Project Z 800 -$1,500 -$1,500 0 $200 $900 1 600 Project Y $400 $600 2 $600 $300 400 $1,000 $200 4 Project Z 200 If the weighted average cost of capital...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 Year Project Y Project Z 0 -$1,500 -$1,500 1 $200 $900 2 $400 $600 $600 $300 4 $1,000 $200 Project Y Project 2 If the weighted average cost of capital (WACC) for each project is...
First Blank: always, sometimes, never
Second Blank: IRR, MIRR, required rate of return
Third Blank: IRR, MIRR, required rate of return
Fourth Blank: IRR method, NPV method
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree....
Dropdown options first 2 blanks: (internal rate of return IRR,
required rate of return, modified internal rate of return MIRR)
Dropdown options 3rd blank: (NPV method, IRR method)
If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. always Projects Y and...
Help
and verified and be clear.
The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company's CFO remembers that the internal rate of return (IRR) of Project Lambda is...
If the projects were independent, which project(s) would be
accepted according to the IRR method?
a) Neither
b) Project A
c) Project B
d) Both Projects A or B
If the projects were mutually exclusive, which project(s) would
be accepted according to the IRR method?
a) Neither
b) Project A
c) Project B
d) Both Projects A or B
The reason is
a) TheNPV and IRR approaches use the same reinvestment rate
assumption and so both approaches reach the same...
1a. Why might a financial analyst use the NPV method for making project decisions instead of the IRR method? ------------------ 1b. Explain the reinvestment rate assumption in the context of a project’s cash flows over time. ------------------ 1c. When we create NPV profiles, what variable is on the y-axis and what variable is on the x-axis? ------------------ 1d. Suppose a firm’s WACC exceeds the IRR for both projects L and S, if the projects are mutually exclusive, which project should...
Which of the following statements is CORRECT? To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the WACC to find the PV. The NPV and IRR methods both assume that cash flows can be reinvested at the WACC. However, the MIRR method assumes reinvestment at the MIRR itself. If two projects have the same cost, and if their NPV profiles cross in the upper right...
Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-YTMcoupongainCorrect 2 of Item 1 on a bond. The equation for calculating the IRR is: CFt is the expected cash flow in Period t and cash outflows are treated...