Answer'

Badgersize Company has the following information for its Forming Department for the month of August. Work in Process In...
Badgersize Company has the following information for its Forming Department for the month of August. $ 80,000 24,000 104,000 53,000 58,000 Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied Total conversion $ 136,000...
Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,900 units Direct materials: 100% complete s 80,eee 24,e00 $104,00e 55,e00 56,000 conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied $138,000 $117,e00 147,000 $264,006e...
Explanations for each answer are
appreciated.
Badgersize Company has the following information for its Forming Department for the month of August Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $80,000 24,000 $ 104,000 48,000 56,000 conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs Direct labor...
The answers that I got before were:
A) for Direct materials is $237,000 and for conversion is
$283,000
B) For direct materials is 3.20 and for conversion is 4.09.
The assignment said that these were not correct. Thank you in
advance for your help!
Badgersize Company has the following information for its Forming Department for the month of August. $ 80,000 24,000 $ 104,000 54,000 58,000 Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20%...
Hi, would you help me with the solution of the problem below? Thanks Tanya Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $ 80,000 Conversion: 20% complete 24,000 Balance in work in process, August 1 $ 104,000 Units started during August 50,000 Units completed and transferred in August 60,000 Work in process (70% complete), August 31 ? Costs charged to Work...
Badgersize Company has the following information for its Forming Department for the month of August:Work in Process Inventory, August 1: 20,000 unitsDirect materials: 100% complete $ 80,000Conversion: 20% complete 24,000Balance in work in process, August 1 $ 104,000Units started during August 50,000Units completed and transferred in August 60,000Work in process (70% complete), August 31 ?Costs charged to Work in Process in AugustDirect materials $ 150,000Conversion costs:Direct labor $ 120,000Overhead applied 132,000Total conversion $ 252,000Assume materials are added at the start...
Work in Process Inventory, August 1 20,000 units Direct materials: 100% complete $80,000 24,000 104,000 45,000 Conversion: 20% complete Balance in work in process, August 1 $ Units started during August Units completed and transferred in August work in process (70% complete), August 31 Costs charged to Work in Process in 57,000 7 August 166,000 Direct materials Conversion costs Direct labor Overhead applied 104,000 142,000 246,000 Total conversion Assume materials are added at the start of processing Instructions a. Calculate...
The following information is available for Department C for the month of August: Units Cost Work in process, August 1 (70% complete) 10,000 Direct materials $ 36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, August 1 $78,000 Started in production during August 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead 61,040 Total costs added during August $217,040 Work in process, August 31 (80% complete) 4,000 Units completed and transferred out 42,000 Materials are added...
The debits to Work in Process—Roasting Department for Morning Brew Coffee Company for August, together with information concerning production, are as follows: Work in process, August 1, 500 pounds, 10% completed $1,610* *Direct materials (500 X $3.1) $1,550 Conversion (500 X 10% X $1.2) $60 $1,610 Coffee beans added during August, 16,000 pounds 48,800 Conversion costs during August 21,073 Work in process, August 31, 800 pounds, 70% completed ? Goods finished during August, 15,700 pounds ? All direct materials are...
The debits to Work in Process—Roasting Department for Morning Brew Coffee Company for August, together with information concerning production, are as follows: Work in process, August 1, 400 pounds, 60% completed $2,232* *Direct materials (400 X $4.5) $1,800 Conversion (400 X 60% X $1.8) 432 $2,232 Coffee beans added during August, 13,000 pounds 57,850 Conversion costs during August 24,605 Work in process, August 31, 700 pounds, 70% completed ? Goods finished during August, 12,700 pounds ? All direct materials are...