A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production run, at a cost of $300. Inventory holding costs will be $10 a year.
a. What run quantity should be used to minimize total annual costs?
b. How many days does it take to produce the optimal run quantity?
c. What is the average amount of inventory?
a. What run quantity should be used to minimize total annual costs?
We have following information:
Daily demand = 80 units
Demand for 1 week = 80 * 5 = 400 units
Annual demand, D = 400 *50 = 20,000 units
Set-up cost S = $300 per order
Annual Inventory holding cost, H = $10 per unit per year
Economic order quantity is the run quantity to minimize the total annual cost
Formula of economic production quantity (EPQ)
EPQ = Q = √ (2 * Annual Demand * Set-up cost/ Inventory holding cost)
Therefore
EPQ = Q = √ (2 * 20,000 *$300 / $10)
EPQ = Q =√ (1,200,000) = 1,095.45 or 1,095 units (rounding off to nearest whole number)
The run quantity to minimize the total annual cost is 1,095 units
b. How many days does it take to produce the optimal run quantity?
The machine will produce the item at a rate of 200 units a day
Therefore,
Length of production run for the optimal run quantity = economic production quantity/ production per day
= 1,095 units /200
= 5.48 days
It will take 5.48 days to produce the optimal run quantity
c. What is the average amount of inventory?
Average inventory level = EPQ / 2 = 1,095 /2 = 547.5 or 548 units
A company is about to begin production of a new product. The manager of the department...
QUESTION 2 A company is about to begin production of a new product. The manager of the department wants to know how often the machine used to produce the current item will be available for the production of the new product. The machine produces the current item at a rate of 220 units a day. 70 units will be used daily in assembling the final product. Assembly takes place five days a week, 50 weeks a year. The manager estimates...
I Think I have the first part down. I just need help on the last
four questions with the 12 day cycle. Thank you!
A company is about to begin production of a new product. The manager of the department wants to know how often the machine used to produce the current item will be available for the production of the new product. The machine produces the current item at a rate of 170 units a day. 80 units will...
1. Basic EOQ Question: The inventory manager of ABC, Ltd., wants to order flour for its bakery in a cost effective manner. The bakery uses an average of 12,000 bags a year. Preparing an order and receiving a shipment of flour involves a cost of $40 per order. Annual carrying costs are $37.50 per bag. REQUIRED: A. Determine the economic order quanity. B. What is the average number of bags on hand? C How many orders will there be per...
A company produces a part that is used in its production process. The company produces the part at a rate of 285 units per day. The daily demand for the product is 165 units. The annual demand for the part is 49 comma 500 units and occurs consistently over the 300 days the company operates yearly. The company incurs a setup cost of $345 each time the item is produced. The cost of carrying the item in inventory is estimated...
Assignment 4.6: Inventory Controls Assignment A 1. A game controller manufacturer uses approximately 31,000 computer chips annually. The chips are used at a steady rate during the 230 days a year that the plan operates. Annual holding cost is $3 per chip, and ordering cost is $120. Determine: a) the optimal order quantity b) the number of workdays in an order cycle 2. The Garble Corporation produces brass rings for its assembly of Fancy Garbles. The firm operates 220 days...
Qwerty Corp. is about to begin production on two homes in a new housing subdivision. Qwerty Corp. anticipates that it will need 80,000 square feet of lumber over its 450 day construction cycle. Ordering and holding costs are $6/order and $8/sq.ft., respectively. Qwerty Corp.'s turnaround time on a lumber order is 2 days. Round intermediate calculations, but round final answer to 2 decimal places. Part 1. How many orders should Qwerty Corp. make to minimize inventory costs? Part 2. At...
Rolf Steps is the production manager for a local manufacturing firm. This company produces staplers and other items. The holding cost is $2 per unit per year. The cost of setting up the production line for this is $25. There are 200 working days per year. The production rate for this product is 80 per day. If the production order quantity is 200 units, what was the daily demand (rounded to the nearest whole unit)? 6 units 7 units 8...
Please show the steps clearly
1. A company is involved in the production of two items (X and Y). The resources need to produce X and Y are twofold, namely machine time for automatic processing and craftsman time for hand finishing. The table below gives the number of minutes required for each item: Table 1: Minutes required for each item Item Machine time Crafstman time Item X 13 20 Item Y 19 29 The company has 40 hours of machine...
Thomas Kratzer is the purchasing manager for the headquarters of a large insurance company chain with a central inventory operation. Thomas’s fastest moving inventory item has a demand of 6000 units per year. The cost of each unit is $100.00, and the inventory carrying cost is $10.00 per unit per year. The average ordering cost is $30.00 per order. It takes about 5 days for an order to arrive, and demand for 1 week is 120 units (this is a...
Summer-Fun, Inc., produces a various commodities related to recreation and leisure. The production manager has developed an aggregate forecast: Apr May Aug Sep Total Mar June July Demand 50 1 44 | 55 | 59 | 50 | 41 51 350 Use the following information to develop aggregate plans. Regular production cost $ 80 per unit Overtime(OT) production cost $ 120 per unit Subcontracting(SC) cost $ 140 per unit Regular capacity 40 units per month Overtime capacity 8 units per...