| Year | Cash flows | Present value@10% | Cumulative Cash flows |
| 0 | (12900) | (12900) | (12900) |
| 1 | 3540 | 3218.18 | (9681.82) |
| 2 | 4560 | 3768.60 | (5913.22) |
| 3 | 1900 | 1427.50 | (4485.72) |
| 4 | 0 | 0 | (4485.72) |
| 5 | 1380 | 856.87 | (3628.85)(Approx). |
Hence discounted Payback period=Last period with a negative cumulative cash flow+(Absolute value of cumulative cash flows at that period/Cash flow after that period).
=0
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 10...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: 2 4 Cash flow:-$11,500 $3,400 $4,280 $1,620 $0 $1,100 Discounted payback period years Should the project be accepted or rejected? O accepted O rejected
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 11 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$12,700 $3,520 $4,520 $1,860 $0 $1,340 Discounted Payback Statistic:
Compute the payback statistic for Project B if the appropriate cost of capital is 10 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "O" (zero).) Project B Time: Cash flow: -512,900 12 $3,540 $4,560 $1,900 $0 $1,380 Payback years Should the project be accepted or rejected? accepted rejected < Prex 6 of 7 Ners > search OM
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$11,000 $3,350 $4,180 $1,520 $300 $1,000 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project t Timet Cash flow: -51,600 $720 $660 Discounted payback period Should the project be accepted or rejected accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time Cash flow -$2,700 $1,160 $990 $1,030 $640 $440 0 2 4 Discounted payback period years Should the project be accepted or rejected? Rejected Accepted
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: −$2,200 $960 $840 $880 $540 $340
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time Cash flow -$1,300 $600 $570 $610 $360 $160 2 4 5 years Should the project be accepted or rejected? O Rejected O Accepted
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow –$12,400 $3490 $4460 $1800 $0 $1280 Payback years