Question

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10.400.000. In the first year

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Percentage of completion = Cost incurred in year 1 / Total cost

Total cost = Cost incurred + Estimated cost = $2250000 + $4000000 = $6250000

Percentage of completion = $2250000 / $6250000 = 0.36 i.e 36%

Revenue to be recognised in year 1 = Contract price * Percentage of completion

= $10400000*36% = $3744000

Gross profit to be recognised in year 1 = Revenue in year 1 - Cost incurred in year 1

= $3744000 - $2250000 = $1494000.

Add a comment
Know the answer?
Add Answer to:
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10.400.000....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Tullis Construction enters into a long -term fixed price contract to build an office tower for...

    Tullis Construction enters into a long -term fixed price contract to build an office tower for $10,700,000. In the first year of the contract Tullis incurs $2,100,000 of cost and the engineers determined that the remaining costs to complete the project are $4,900,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the completed- contract method? OA....

  • Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....

    Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? 18. Tullis Construction enters into...

  • Hepner Products enters into a contract with Tullis to sell three different products. The total price...

    Hepner Products enters into a contract with Tullis to sell three different products. The total price is $350,000 Each of the products is a separate performance obligation. Based on the information presented in the table, what is the allocated transaction price of product Z using the adjusted market assessment approach? (Round intermediary percentages to the nearest hundredth percent, and round your final answer to the nearest whole number.) Product Standalone Price Market Price X $150,000 $130,000 Y $125,000 $135,000 Z...

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • A construction company entered into a fixed-price contract to build an office building for $20 million....

    A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $44 million....

    A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $48 million....

    A construction company entered into a fixed-price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $10 million....

    A construction company entered into a fixed-price contract to build an office building for $10 million. Construction costs incurred during the first year were $2 million and estimated costs to complete at the end of the year were $3 million. The building was completed during the second year. Construction costs incurred during the second year were $4 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • The Hindenburg Corporation (SC) signed a $6 million contract in 20x1 to build an office tower. Data on the contract...

    The Hindenburg Corporation (SC) signed a $6 million contract in 20x1 to build an office tower. Data on the contract is as follows: 20x1 Costs incurred during year Expected costs to complete Billings 20x2 1,500,000 1,700,000 20x4 800,000 $1,600,000 3,400,000 2,500,000 20x3 1,400,000 900,000 3,500,000 Required - For each of the parts below, prepare the 'mini income statement for the project for each year and calculate the net investment of the project that will be shown on the balance sheet...

  • A construction company entered into a fixed-price contract to build an office building for $30 million....

    A construction company entered into a fixed-price contract to build an office building for $30 million. Construction costs incurred during the first year were $10 million and estimated costs to complete at the end of the year were $15 million. During the first year the company billed its customer $11 million, of which $3 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter you answers in whole...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT