Question

Problem 6: Knowing that the IRR for 4 projects are 16.94%, 12.69%, 14.33% and 14.81% and...

Problem 6: Knowing that the IRR for 4 projects are 16.94%, 12.69%, 14.33% and 14.81% and there is an annual inflation rate of 5%. What are the IRR's of the projects after the inflation? and which project is better?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Inflation is 5%

IRR after inflation is IRR before inflation - 5%

IRR1=16.94%-5%=11.94%

IRR2=12.69%-5%=7.69%

IRR3=14.33%-5%=9.33%

IRR4=14.81%-5%=9.81%

Add a comment
Know the answer?
Add Answer to:
Problem 6: Knowing that the IRR for 4 projects are 16.94%, 12.69%, 14.33% and 14.81% and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 11-12 IRR and NPV A company is analyzing two mutually exclusive projects, S and L,...

    Problem 11-12 IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 1 3 4 Project S Project L The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the -$1,000 $876.65 $15 $250 $15 $773.59 -$1,000 $5 $260 $380 higher IRR.) Round your answer to two decimal places

  • 11-2: Net Present Value (NPV) 11-3: Internal Rate of Return (IRR) Problem Walk-Through IRR and NPV...

    11-2: Net Present Value (NPV) 11-3: Internal Rate of Return (IRR) Problem Walk-Through IRR and NPV A company is analyzing two mutually exclusive projects, s and L, with the following cash flows: 0 2 3 4 Project S$1,000T $906.76 $240 $5 $10 Project L$1,000 $0$250 $380 $792.79 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: 1 better project may or may not be the one with the higher IRR.) Round your answer to two...

  • Problem 11-12 IRR and NPV A company is analyzing two mutually exclusive projects, S and L,...

    Problem 11-12 IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 1 2 3 Project S -$1,000 $868.18 $250 $10 $15 Project L - $1,000 $0 $250 $420 $808.19 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.

  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • IRR-Mutually exclusive projects Bell Manufacturing is attempting to choose the better of two mutually exclusive projects...

    IRR-Mutually exclusive projects Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the firm's warehouse capacity. The relevant cash flows for the projects are shown in the following table: B . The firm's cost of capital is 13%. a. Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs. b. Which project is preferred? a. The internal rate of return (IRR) of project X...

  • 4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound...

    4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound annual rate of return that a project generates based on its up-front cost and subsequent cash flows. Consider the case of Blue Llama Mining Company: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. The company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to...

  • IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...

    IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $879.99 $260 $15 $10 Project L -$1,000 $0 $260 $380 $789.53 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. NPV A project has annual cash flows...

  • 11.12 IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with...

    11.12 IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:    0 1 2 3 4 Project S -$1,000 $887.39 $260 $10 $5 Project L -$1,000 $10 $250 $420 $780.08 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. ____%

  • IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...

    IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 1 2 Project S - $1,000 $902.08 $240 $5 $15 Project L - $1,000 $5 $260 $380 $838.13 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT