Question

Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...

Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project M
Time: 0 1 2 3 4 5
Cash flow: −$1,900 $530 $660 $700 $780 $280

NPV?

Should the project be accepted or rejected?

  • accepted

  • rejected

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Solution:
a. NPV     476.15
Working Notes:
Notes: NPV is the net of present value of cash flows during the life of project which includes cash outflows and cash inflows.
A B C = A x B
Time Cash flow PVF @ 8% Present Value
0 -1900 1 -1900
1 530 0.925926 490.7407
2 660 0.857339 565.8436
3 700 0.793832 555.6826
4 780 0.735030 573.3233
5 280 0.680583 190.5633
NPV 476.15
Notes: PVF is calculated @ r% = 1/(1+r%)^n    for given case used is (1/(1.08)^n) where n is the period for which PVF is calculated.
b.
Accepted
Working Notes:
Project M Should Be accepted as its NPV is positive 476.15 means it is able to generate more than required cost of capital of 8% , hence the project should be accepted.
Please feel free to ask if anything about above solution in comment section of the question.
Add a comment
Know the answer?
Add Answer to:
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...

    Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign Do not round intermediate calculations and round your final answer to 2 decimal places.) Protect Time: Cash flow: $1,900 $530 $660 $700 $780 $280 NPV Should the project be accepted or rejected? accepted rejected

  • Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....

    Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: . Cash flow: 1. $710 2. $2,380 3. $700 4. $660 5 $280 $2,400 NPV Should the project be accepted or rejected? Orejected accepted

  • Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative...

    Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$1,400 $430 $560 $600 $680 $180 Should the project be accepted or rejected? accepted rejected

  • Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...

    Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$2,900 $650 $780 $820 $900 $400

  • Compute the NPV for Project K if the appropriate cost of capital is 5 percent. (Negative...

    Compute the NPV for Project K if the appropriate cost of capital is 5 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: Cash flow: 0 1 $10,200 $5,100 2 $6,100 3 $6,100 4 $5,100 5 $10,200 NPV Should the project be accepted or rejected? accepted O rejected

  • Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent....

    Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,200 $630 $2,180 –$660 $580 –$240 NPV= Should the project be accepted or rejected?

  • Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....

    Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Ne minus sign. Do not round intermediate calculations and round your final answer to 20 Project Y Time: Cash flow: $8,400 $3,710 $4,540 $1,880 $660 NPV Should the project be accepted or rejected? rejected • accepted

  • Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....

    Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: Cash flow: -$1,300 $470 $1,780 $580 $420 -$160 NPV Should the project be accepted or rejected? rejected accepted

  • Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....

    Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,200 $3,670 $4,500 $1,840 $620 NPV $ Should the project be accepted or rejected? Rejected Accepted

  • Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....

    Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -68,300 $3,690 64,520 61,960 6640 NPV Should the project be accepted or rejected? rejected Daccepted

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT