CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S requires an initial outlay at t = 0 of $17,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Explain.
NPV = PV of Cash Inflows - PV of Cash Outflows
Project S:
| Year | CF | PVF @12% | Disc CF |
| 0 | $ -17,000.00 | 1.0000 | $ -17,000.00 |
| 1 | $ 5,000.00 | 0.8929 | $ 4,464.29 |
| 2 | $ 5,000.00 | 0.7972 | $ 3,985.97 |
| 3 | $ 5,000.00 | 0.7118 | $ 3,558.90 |
| 4 | $ 5,000.00 | 0.6355 | $ 3,177.59 |
| 5 | $ 5,000.00 | 0.5674 | $ 2,837.13 |
| NPV | $ 1,023.88 | ||
Project L:
| Year | CF | PVF @12% | Disc CF |
| 0 | $ -30,000.00 | 1.0000 | $ -30,000.00 |
| 1 | $ 8,750.00 | 0.8929 | $ 7,812.50 |
| 2 | $ 8,750.00 | 0.7972 | $ 6,975.45 |
| 3 | $ 8,750.00 | 0.7118 | $ 6,228.08 |
| 4 | $ 8,750.00 | 0.6355 | $ 5,560.78 |
| 5 | $ 8,750.00 | 0.5674 | $ 4,964.98 |
| NPV | $ 1,541.79 | ||
Project L is selected as it has higher NPV
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S requires an initial outlay at t = 0...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $36,000, and its expected cash flows would be $14,550 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,500, and its expected cash flows would be $13,100 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVs > NPVĻ. b. Project L,...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years, Mutually exclusive Project L requires an initial outlay at t = 0 of $48,000, and its expected cash flows would be $9,550 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer a. Project L, since the NPV > NPV- b. Both...
Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flows would be $9,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVS > NPVL. II. Both Projects and L, since both projects have NPV's...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...
Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,000, and its expected cash flows would be $14,800 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. Oa. Project L, since the NPVL > NPVS. O b. Neither...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $8,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O a. Both Projects S and L, since both projects have...