I am having trouble figuring out the standard cost for the direct labor and the Manufacturing Overhead


| Cost Element | Standard Cost | Actual Cost | Variance | |
| Materials | ||||
| Standard | $ 288,000 | $ 1,380 | U | |
| Actual | $ 289,380 | |||
| Labor | ||||
| Standard | $ 315,000 | $ (5,880) | F | |
| Actual | $ 309,120 | |||
| Manufacturing Overhead | ||||
| Standard | $ 126,000 | $ (2,352) | F | |
| Actual | $ 123,648 | |||
| Total | $ 729,000 | $ 722,148 | $ (6,852) | |
| Variance | $ (6,852) | F | ||
Here is the formula version
| Cost Element | Standard Cost | Actual Cost | Variance | |
| Materials | ||||
| Standard | =4500*4*16 | =289380-288000 | U | |
| Actual | =18200*15.9 | |||
| Labor | ||||
| Standard | =4500*5*14 | =309120-315000 | F | |
| Actual | =22400*13.8 | |||
| Manufacturing Overhead | ||||
| Standard | =C7*0.4 | =123648-126000 | F | |
| Actual | 123648 | |||
| Total | =SUM(C4:C11) | =SUM(D4:D11) | =SUM(E4:E11) | |
| Variance | =D13-C13 | F | ||
I am having trouble figuring out the standard cost for the direct labor and the Manufacturing...
Im having trouble with figuring out how to find the quantity and
Price variances.
Is there a formula? Thanks
**I figured out how to get the price variance, Just struggling
with the quantity variance. Thanks
West Texas Chemical Company manufactures a product called Kylon, which requires three raw materials. Production is in batches of 1,000 gallons of finished product. The firm uses standard costs as a control device. Its standard costs for materials for each batch of Kylon have been...
Problem 16-64 (Algo) Manufacturing Variances (LO 16-5) Delta Products prepares its budgets on the basis of standard costs. A responsibility report is prepared monthly showing the differences between master budget and actual results. Variances are analyzed and reported separately. There are no materials inventories. The following information relates to the current period: $ 24 100 Standard costs (per unit of output) Direct materials, 6 gallons @ $4.00 per gallon Direct labor, 5.00 hours @ $20.00 per hour Factory overhead Variable...
Highfill Corporation's variable overhead is applied on the basis of direct labor-hours. The standard cost card for product D80D specifies 6.4 direct labor-hours per unit of D80D. The standard variable overhead rate is $5.90 per direct labor-hour. During the most recent month, 1,100 units of product D80D were made and 7,100 direct labor-hours were worked. The actual variable overhead incurred was $45,230. Required: a. What was the variable overhead rate variance for the month? b. What was the variable overhead...
Delta Products prepares its budgets on the basis of standard costs. A responsibility report is prepared monthly showing the differences between master budget and actual results. Variances are analyzed and reported separately. There are no materials inventories. The following information relates to the current period: Standard costs (per unit of output) Direct materials, 6 gallons @ $2.00 per gallon $ 12 Direct labor, 3 hours @ $36 per hour 108 Factory overhead Variable (25% of direct labor cost) 27...
Delta Products prepares its budgets on the basis of standard
costs. A responsibility report is prepared monthly showing the
differences between master budget and actual results. Variances are
analyzed and reported separately. There are no materials
inventories. The following information relates to the current
period:
Delta Products prepares its budgets on the basis of standard costs. A responsibility report is prepared monthly showing the differences between master budget and actual results. Variances are analyzed and reported separately. There are no...
Huron Company produces a
commercial cleaning compound known as Zoom. The direct materials
and direct labor standards for one unit of Zoom are given below:
Standard Quantity or Hours Standard Price or Rate Standard Cost
Direct materials 6.00 pounds $ 2.30 per pound $ 13.80 Direct labor
0.50 hours $ 10.00 per hour $ 5.00 During the most recent month,
the following activity was recorded: Eleven thousand pounds of
material were purchased at a cost of $2.10 per pound. All...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $10.00 per pound$50.00Direct labor: 3 hours at $17 per hour51.00Variable overhead: 3 hours at $7 per hour21.00Total standard variable cost per unit$122.00 The company also established the following cost formulas for its selling expenses: Fixed Cost per MonthVariable Cost per Unit SoldAdvertising$330,000Sales salaries and commissions$360,000$25.00Shipping expenses$16.00 The planning budget for March was...
**I have found the correct answers for everything but price
variance and efficiency variance. Please show work. Thank you
Problem 16-59 Manufacturing Variances (LO 16-5) Delta Products prepares its budgets on the basis of standard costs. A responsibility report is prepared monthly showing the differences between master budget and actual results. Variances are analyzed and reported separately. There are no materials inventories. The following information relates to the current period Standard costs (per unit of output) Direct materials, 7 gallonsS4.00...
Rip Tide Company manufactures surfboards. Its standard cost information follows: Direct materials (fiberglass) Direct labor Variable manufacturing overhead (based on direct labor hours) Fixed manufacturing overhead ($24,000 300 units) Standard Quantity 15 sq. ft. 10 hrs. 10 hrs. Standard Price (Rate) $ 5 per sq. ft. $15 per hr. $ 6 per hr. Standard Unit Cost $ 75.00 150.00 60.00 80.00 Rip Tide has the following actual results for the month of June: Number of units produced and sold Number...
Direct materials-1 pound plastic at $6.00per pound Direct labor-2.0 hours at $12.20 per hour Variable manufacturing owerhead Fixed manufacturing overhead Total standard cost per unit $6.00 2440 15.00 13.00 $58.40 The predetermined manufacturing overhead rate is $14.00 per direct labor hour ($28.00 2.0 Itwas computed from a master manufacturing overhead budget based on normal production of 10,000 direct labor hours (5,000 units) for the month. The master budget showed total variable costs of $75,000$7.50 per hour) and total foxed overhead...