Question
Utilizing the Kaizan costing system improves efficiency and therefore over time, reduces product cost.
In your own words, how are the classes and stages of benchmarking supportive to efficiencies in product costing?
Solution 1:
Kaizen Costing System:
Kaizen costing system is a mechanism that aims at continual reduction in the cost. However, it does not aim in any major improvement in innovation. It starts after the product is designed and strives to make continuous improvements in relatively small activities (or processes) in the production. Team work is involved to bring radical changes. Team work includes complete cooperation and commitments from the workers. This technique is developed in manufacturing sector with aim of lowering the defects, eliminating waste, increase production, encouraging workers by holding them accountable for the success in production.
The selling price is determined by the market. It is important to reduce the cost to maximise the profits. The main purpose of kaizen costing system is to bring the cost reduction below the standard level (of selling price), with zero (or no) effect on quality, staff and safety. It considers factors such working closely with the suppliers to reduce the cost in the production process, doing product re-designing at lesser cost, and reducing waste.
Kaizen costing system aims at reducing cost at smaller level in each processes of the production and gradually these smaller costs saving at each process in the production will lead to larger cost saving as a whole.
Kaizen costing system approach is usually by Plan-Do-Check-Act Cycle. In the Plan step we try to identify the problem we face in the production process. In Do step we test the potential solution. In Check step we will analyse the plan we implemented. In Act step the best analysed solution will be implemented in the production process.
Solution 2:
Efficiency of product costing involves from time the product is in design. It involves.
Question Utilizing the Kaizan costing system improves efficiency and therefore over time, reduces product cost. In...
Utilizing the Kaizan costing system improves efficiency and therefore over time, reduces product cost. In your own words, how are the classes and stages of benchmarking supportive to efficiencies in product costing?
utilizing the activity based costing system information provided below, select the correct product margin activity cost pool assembly $600,000, 5,000 machine hours processing orders $300,000, 500 orders inspection $200,000, 400 inspection hours. The company makes 5000 units of product XYZ a year, requiring a total of 1000 machine hours, 10 orders and 10 inspection hours per year. the products direct materials cost is $100 per unit and it's direct labor cost is $50 per unit. the product sells for $200...
Utilizing the activity-based costing system information provided below, select the correct product margin. Total Activity Activity Cost Pool Assembly Processing orders 5,000 machine-hours Total Cost $600,000 $300,000 $200,000 500 orders Inspection 400 inspection-hours The company makes 5,000 units of Product XYZ a year, requiring a total of 1,000 machine-hours, 10 orders, and 10 inspection-hours per year. The product's direct materials cost is $100.00 per unit and its direct labor cost is $50.00 per unit. The product sells for $200.00 per...
QUESTION 13 Activity-based costing systems conform to Generally Accepted Accounting Principles and can therefore be used for both internal and external reporting. O True O False QUESTION 14 Hane Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pools Activity Rate Assembling products.... Processing customer orders... Setting up batches... $8.90 $31.23 $43.72 per assembly hour per customer order per batch Data for one of the company's products follow: Product U94W Number...
QUESTION 2 Alpha company makes a single product and uses a standard costing system that applies overhead on the basis of direct labor hours. For the most recent period, the VOH spending variance was $80,000 F, and the VOH Efficiency Variance was $100,000 U. The company budgeted making 4,800 units at 3.5 hours each with $924,000 of VOH. The company actually produced 4,000 units. How many direct labor hours were used? (Please round to nearest whole direct labor hour at...
QUESTION 32 The cost of a completed job in a job-order costing system typically consists of the actual direct materials cost of the job, the actual direct labor cost of the job, and the manufacturing overhead cost applied to the job. True 2.157 points False QUESTION 33 An activity in activity-based costing is an event that causes the consumption of overhead resources. True 2.857 False QUESTION 34 If a company has a great deal of product diversity, activity-based costing will...
Cycle Time, Velocity, Product Costing Mulhall, Inc., has a JIT system in place. Each manufacturing cell is dedicated to the production of a single product or major subassembly. One cell, dedicated to the production of mopeds, has four operations: machining, finishing, assembly, and qualifying (testing). The machining process is automated, using computers. In this process, the model’s frame and engine are constructed. In finishing, the frame is sandblasted, buffed, and painted. In assembly, the frame and engine are assembled. Finally,...
Question 3 (20 marks) Costing will eventually decide how much a customer will have to pay for a product and therefore is a must in any design. a. Differentiate between "design cost" and "product cost". (5 marks) b. Propose three cost objectives in the early design phase and another three for the later design stages. (5 marks) c. The list price of a product can be broken down into the following costs: discount, profit, selling expenses, overhead, tooling, labour, purchased...
Question 4 Ellis Ltd uses an operating costing system and produces two products. The same conversion cost is charged to all products passing through a common process. Details for October are: Machining Assembly Painting Direct Materials - Product A $88,000 Direct Materials - Product B $66,000 $1,600 Direct Labour $51,600 $12,000 - 9,000 4,200 Machine Hours Worked 1,080 Units Commenced and Completed: Product A Product B 10,000 5,000 10,000 5,000 2,000 Both products commence production in Machining before passing to...
QUESTION 7 Likert company manufactures extremely accurate scales. They use a standard costing system. Last year the company projected that 290,000 scales would be produced. When Likert company closed out manufacturing overhead, they recorded a $116,000 debit to the FOH Budget Variance and a $135,000 credit to the FOH Volume Variance. Likert company budgeted $2,409,000 of fixed overhead. What was the actual amount of fixed overhead? QUESTION 8 If a firm uses direct labor hours as its overhead driver, a...