| Q1) | Direct Labor Price Variance = Actual Hours Worked * ( Standard RAte - Actual RAte) | |||||||||
| $3150 (U) = 6300 Hours * ($9 - Actual Rate) | ||||||||||
| -3150 =56700 -6300* Actual Rate | ||||||||||
| Actual Rate = $9.5 Per hour | ||||||||||
| Therefore option "c" is correct. | ||||||||||
| Q2) | Actual DM Cost Per Unit = $96000/24000 | |||||||||
| =$4 per kg | ||||||||||
| Direct Material Price Variance = Actual Kg * (Std Rate - Actual Rate) | ||||||||||
| 3600(U) = 24000 * (std rate -4) | ||||||||||
| -3600 = 24000 std rate -96000 | ||||||||||
| Standard Rate = $3.85 | ||||||||||
| Therefore option "b" is correct. | ||||||||||
| Q3) | Standard DM cost per unit | |||||||||
| Per unit | ||||||||||
| Tomatoes | $ 2.25 | |||||||||
| (150000Kg/40000 units *0.6 per kg) | ||||||||||
| Olive oil | $ 0.02 | |||||||||
| (400 litres/40000*$2 per liters) | ||||||||||
| Others | $ 0.60 | |||||||||
| Total | $ 2.87 | |||||||||
| Therefore option "a" is correct. | ||||||||||
| Q4) | Standard Cost | |||||||||
| Eggs | 0.3 | |||||||||
| (2*0.15) | ||||||||||
| Slice | 0.23 | |||||||||
| (1*0.23) | ||||||||||
| Direct Labor Cost | 1.5 | |||||||||
| (0.15*10) | ||||||||||
| Factory Overhead | 0.15 | |||||||||
| Total | 2.18 | |||||||||
| Therefore option "d" is correct. | ||||||||||
| 5) | correct optio = b | |||||||||
Circle the correct answer (2 points each) 11/21/2019 Name: 1. The standard number of hours that...
Miguez Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 2.3 liters $ 7.00 per liter $ 16.10 Direct labor 0.7 hours $ 22.00 per hour $ 15.40 Variable overhead 0.7 hours $ 2.00 per hour $ 1.40 The company budgeted for production of 2,600 units in September, but actual production was 2,500 units. The company used 5,440 liters of direct material and 1,680 direct labor-hours...
Miguez Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 2.3 liters $ 7.00 per liter $ 16.10 Direct labor 0.7 hours $ 22.00 per hour $ 15.40 Variable overhead 0.7 hours $ 2.00 per hour $ 1.40 The company budgeted for production of 2,600 units in September, but actual production was 2,500 units. The company used 5,440 liters of direct material and 1,680 direct labor-hours...
Landram Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Direct materials 2.0 liters $7.00 per liters Direct labor 1.1 hours $13.00 per hour Variable overhead 1.1 hours $7.00 per hour The company produced 4,800 units in April using 10,290 liters of direct material and 2,270 direct labor-hours. During the month, the company purchased 10,860 liters of the direct material at $7.35. per liter. The actual direct labor rate was $13.60 per...
Kennedy Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost per Unit Direct materials 8.2 pounds $7.00 per pound $57.40 Direct labor 0.4 hours $20.00 per hour $8.00 Variable overhead 0.4 hours $2.00 per hour $0.80 The company budgeted for production of 2,400 units in June, but actual production was 2,500 units. The company used 19,850 pounds of direct material and 980 direct labor-hours to produce this output. The company...
Morgan Manufacturing makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost per Unit Direct materials 6.5 kilos $1.00 per kilo $6.50 Direct labor 0.3 hours $10.00 per hour $3.00 Variable overhead 0.3 hours $4.00 per hour $1.20 In January the company's budgeted production was 7,400 units but the actual production was 7,200 units. The company used 45,580 kilos of the direct material and 2,400 direct labor-hours to produce this output. During...
Kartman Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 7.3 pounds $ 7.80 per pound $ 56.94 Direct labor 0.4 hours $ 32.00 per hour $ 12.80 Variable overhead 0.4 hours $ 4.80 per hour $ 1.92 In June the company's budgeted production was 4,200 units but the actual production was 4,300 units. The company used 22,950 pounds of the direct material and 2,370 direct...
a) The Walter Group provides the following data for June 2019 when 15,000 units were manufactured. Standard Material cost (per Unit) 8.50kg @ $7.50 per Kg. Actual Material cost (Per Unit) 6.75Kg @ $13.5 per Kg. Standard Labour cost (Per Unit) 5.5hrs @ $15 per hour Actual Labour cost (Per Unit) 6.5hrs @ $12.2 per hour Calculate the following: 1. Direct Material Variance 2. Direct Material Quantity/Usage Variance 3. Total Material Cost Variance 4. Direct Labour rate Variance 5. Direct...
Black and Decker Corporation has the following information is for their standard and actual costs: Standard Costs: Budgeted units of production - 9,000 (100% of capacity) Standard material per unit - 12 lbs. Standard material cost - $14.00 per pound Standard labor hours per unit - 12 Standard labor rate - $29.00 per hour Standard variable overhead rate - $7.50 per labor hour Budgeted fixed overhead - $729,000 Fixed overhead rate is based on budgeted labor hours at 100% capacity...
Standard Standard Price (1) Standard Quantity or Hours 2.30 pounds 1.ee hours 1.00 hours or Rate Inputs Direct materials Direct labor Variable manufacturing overhead (1) X (2) $39.10 $17.00 per pound $16.10 per hour $ 9.20 per hour Total standard cost per unit Direct materials Direct labor Variable manufacturing overhead Total Variance Reported Standard Price Quantity or Cost or Rate Efficiency 5782,000 $ 13,920 F $ 34,000 U $322,000 $ 4,200 $ 16,100 U $184,000 $4,700 F S "Applied to...
tic microcomputer cases at a selling price of $10.00 machine hours. The standard variable costs per Containers, Inc. produced 62,500 and sold 59,000 plastic micr each. Manufacturing overhead is allocated on the basis of machine hours. computer case were: Quantity Rate Direct Materials 1.5 kg $ 1.20 per kg Direct Labour 0.50 labour hours $ 15.00 per hour Variable Overhead 0.20 machine hours $6.00 per hour Total $1.80 7.50 1.20 Information regarding fixed overhead includes the following: Budgeted Fixed Overhead:...