Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows:
| Factory 1 | Factory 2 | ||||
| Estimated factory overhead cost for fiscal | |||||
| year beginning August 1 | $468,920 | $633,600 | |||
| Estimated direct labor hours for year | 8,800 | ||||
| Estimated machine hours for year | 24,680 | ||||
| Actual factory overhead costs for August | $37,590 | $54,600 | |||
| Actual direct labor hours for August | 790 | ||||
| Actual machine hours for August | 1,930 | ||||
a. Determine the factory overhead rate for
Factory 1.
$ per machine hour
b. Determine the factory overhead rate for
Factory 2.
$ per direct labor hour
c. Journalize the entries to apply factory overhead to production in each factory for August. If an amount box does not require an entry, leave it blank.
| Factory 1 | |||
| Factory 2 | |||
d. Determine the balances of the factory overhead accounts for each factory as of August 31, and indicate whether the amounts represent overapplied factory overhead or underapplied factory overhead.
| Factory 1 | $ | ||
| Factory 2 | $ |
a. Determine the factory overhead rate for
Factory 1.
$468920/24680 = 19 per machine hour
b. Determine the factory overhead rate for
Factory 2.
$633600/8800 = 72 per direct labor hour
c. Journalize the entries to apply factory overhead to production in each factory for August. If an amount box does not require an entry, leave it blank.
| Factory 1 | Work in process (1930*19) | 36670 | |
| Factory overhead | 36670 | ||
| Factory 2 | Work in process (790*72) | 56880 | |
| Factory overhead | 56880 |
d. Determine the balances of the factory overhead accounts for each factory as of August 31, and indicate whether the amounts represent overapplied factory overhead or underapplied factory overhead.
| Factory 1 | $36670-37590 = 920 | Under applied | |
| Factory 2 | 56880-54600 = 2280 | Over applied |
Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 $297,180 $993,300 12,900 Estimated factory overhead cost for fiscal year beginning August 1 Estimated direct labor hours for year Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $18,500,000 $44,000,000 Estimated direct labor hours for year 800,000 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $18,500,000 $44,000,000 Estimated direct labor hours for year 800,000 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $297,180 $993,300 Estimated direct labor hours for year 12,900 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours hours in Factory 2. Estimated factory overhead costs direct labot hours, and machine hours are as follow Factory2 7700 $1,110 DOO 3 15 000 Estimated factory overhead cost for fiscal year beginning August 1 Estimated direct labor hours for year Estimated machine hours for year Actual factory overhead costs for August Actual direct labor...
Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $519,680 $610,400 10,900 Estimated direct labor hours for year Estimated machine hours for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $1,516,700 $1,074,600 Estimated direct labor hours for year 29,850 Estimated machine hours for year 52,300 Actual factory overhead costs for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $1,450,400 $800,250 Estimated direct labor hours for year 24,250 Estimated machine hours for year 51,800 Actual factory overhead costs for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $674,520 $984,900 Estimated direct labor hours for year 14,700 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $740,250 $735,000 Estimated direct labor hours for year 9,800 Estimated machine hours for...