Question

Part 1: Explain how to compute the cash payback method. Explain when a result would be rejected or accepted using the cash pa

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cash payback method is used to decide whether company should invest in capital projects or not. This method calculates the time period over which it's original cost will be recovered. For example suppose the initial cost is $100000. And each year cash inflow will be $20000 so in 5 years total cost will be recovered. So cash payback period will be 5 years for this project.

This project doesn't cosider the time value of money.

Following formula will be used to calculate payback period

= Initial investment / cash inflow per year

If cash inflow per year is different then we have to make a table calculating cumulative cash recovered.

There are two methods using this payback period to decide whether to accept or not

1. If company have s pre decided time period that is for example say company wants to revover cost in 3 years so all projects with payback period of more than 3 years will be rejected.

2. If there are more than one alternative so company will calculate payback period for all of them and the the alternative with least payback period will be accepted.

Feel free to ask any queries..

Also plz upvote it means a lot.. thank you

Add a comment
Know the answer?
Add Answer to:
Part 1: Explain how to compute the cash payback method. Explain when a result would be...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...

    Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...

  • Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent...

    Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: 0 -$2,300 1 $870 2 $870 3 $780 4 $560 5 $360 Payback years Should the project be accepted or rejected? accepted O rejected

  • Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent...

    Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: 0 -$2,300 1 $870 2 $870 3 $780 4 $560 5 $360 Payback years Should the project be accepted or rejected? accepted O rejected

  • Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...

    Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: -$2,800 $1,070 $1,020 $889 $660 $460 Payback years Should the project be accepted or rejected? accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: Cash flow: 0 -$12,500 1 $3,500 2 $4,480 3 $1,820 4 $0 5 $1,300 Payback years Should the project be accepted or rejected? accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: Cash flow: -$11,000 $3,350 $4,130 $1,520 $0 $1,000 Payback years Should the project be accepted or rejected? accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$11,400 $3,390 $4,260 $1,600 $0 $1,080 Should the project be accepted or rejected? accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$12,800 $3,530 $4,540 $1,880 $0 $1,360 Should the project be accepted or rejected? accepted rejected

  • Compute the discounted payback statistic for Project if the appropriate cost of capital is 8 percent...

    Compute the discounted payback statistic for Project if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project t Timet Cash flow: -51,600 $720 $660 Discounted payback period Should the project be accepted or rejected accepted rejected

  • Compute the payback statistic for Project B if the appropriate cost of capital is 10 percent...

    Compute the payback statistic for Project B if the appropriate cost of capital is 10 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "O" (zero).) Project B Time: Cash flow: -512,900 12 $3,540 $4,560 $1,900 $0 $1,380 Payback years Should the project be accepted or rejected? accepted rejected < Prex 6 of 7 Ners > search OM

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT