| Overhead assigned | |||||||
| Standard Model | $ 1,84,448 | ||||||
| Deluxe Model | $ 2,18,860 | ||||||
| Overhead assigned | |||||||
| Standard Model | $ 1,12,920 | ||||||
| Deluxe Model | $ 2,90,390 | ||||||
| Workings: | |||||||
| Traditional cost system: | |||||||
| Predetermined overhead rate | = | Total overhead / Total Machine hours | |||||
| = | $403310 / (26800 + 31800) | ||||||
| = | $ 6.8824 | ||||||
| Total Machine hours | Predetermined overhead rate | Overhead assigned | |||||
| (i) | (ii) | (i) X (ii) | |||||
| Standard Model | 26,800 | $ 6.8824 | $ 1,84,448 | ||||
| Deluxe Model | 31,800 | $ 6.8824 | $ 2,18,860 | ||||
| Activity based costing: | |||||||
| Predetermined overhead rate | = | Total overhead / Total Machine hours | |||||
| = | $403310 / (26800 + 31800) | ||||||
| = | $ 6.8824 | ||||||
| Number of Material moves | Weight | Overhead cost | Number of Setups | Weight | Overhead cost | Total overhead assigned | |
| (i) | (ii) | (i) X (ii) = (a) | (iii) | (iv) | (iii) X (iv) = (b) | (a) + (b) | |
| Standard Model | 640 | $ 0.4051 | $ 76,800 | 120 | $ 0.1690 | $ 36,120 | $ 1,12,920 |
| Deluxe Model | 940 | $ 0.5949 | $ 1,12,800 | 590 | $ 0.8310 | $ 1,77,590 | $ 2,90,390 |
| 1580 | $ 1.0000 | $ 1,89,600 | 710 | $ 1.0000 | $ 2,13,710 | $ 4,03,310 | |
E4-14 (Algo) Assigning Costs Using Traditional System, ABC System (LO 4-1, 4-3, 4-4,4-5) Julio produces two...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow: Number of machine hours Number of material moves Number of setups Standard Model Deluxe Model 27,000 32,000 650 950 120 600 Total estimated overhead costs are $394,160,...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow. Number of machine hours Number of material moves Number of setups Standard Model 25,000 550 80 Deluxe Model 30,000 850 500 Total estimated overhead costs are $303,560,...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow: Number of machine hours Number of material moves Number of setups Standard Model 26,100 605 65 Deluxe Model 31,100 905 555 Total estimated overhead costs are $347.760,...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow: Standard Model Deluxe Model Number of machine hours 26,600 31,600 Number of material moves 630 930 Number of setups 100 580 Total estimated overhead costs are $406,120,...
Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow Number of machine hours Number of material moves Number of setups Standard ModelDeluxe Model 30,800 890 540 25,800 590 70 Total estimated overhead costs are $347,100, of...
Pre-Built Problems a Julio produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has identified two cost pools: materials handling and setup. The collected data follow Number of machine hours Number of material moves Number of setups Total estimated overhead costs are $368.360, of which $189.800 is assigned to the...
Jullo produces two types of calculator, standard and deluxe. The company is currently using a traditional costing system with machine hours as the cost driver but is considering a move to activity-based costing. In preparing for the possible switch, Julio has Identified two cost pools: materials handling and setup. The collected data follow: Number of machine hours Number of material moves Number of setups Standard Model 25,7ee 585 85 Deluxe Model 30,7ee 885 535 Total estimated overhead costs are $362,930,...
E4-12 Assigning Costs Using Traditional System, ABC System [LO 4-1, 4-3, 4-4, 4-5, 4-6] Bunker makes two types of briefcase, fabric and leather. The company is currently using a traditional costing system with labor hours he cost driver but is considering switching to an activity-based costing system. In preparation for the possible switch, Bunker has identified two activity cost pools: materials handling and setup. Pertinent data follow: Leather Case 11,000 Number of labor hours Number of material moves Number of...
PA4-1 (Algo) Assigning Costs Using Traditional System, ABC System (LO 4-1, 4-3, 4-4, 4-6) Hazelnut Corp. manufactures lawn ornaments. It currently has two product lines, the basic and the luxury. Hazelnut has a total of $155,581 in overhead. The company has identified the following information about its overhead activity cost pools and the two product lines: Cost Activity Cost Pools Cost Driver to Pool Materials handling Number of moves $ 3,311 Quality control Number of inspections $ 28,670 Machine maintenance...
PA4-1 Assigning Costs Using Traditional System, ABC System [LO 4-1, 4-3, 4-4, 4-6] Hazelnut Corp. manufactures lawn ornaments. It currently has two product lines, the basic and the luxury. Hazelnut has a total of $175.910 in overhead. The company has identified the following information about its overhead activity cost pools and the two product lines: Cost Quantity/Amount ConsumedQuantity/Amount Consumed / Assigned by by Activity Cost Pools Cost Driver to Pool Basic Luxury Materials handling Number of moves $ 4,050 28...