A 1,500-foot subdivision street is to be constructed. The layout will be completed in 3 days, the fill will be brought in over the course of 8 days, the compaction/grading will be completed in 5 days, the asphalt topping will be done in 3 days, and the striping will take 1 day to complete. Using a minimum float guideline of 1 day, develop a linear schedule for this project. What is the project duration if no activities are to be interrupted? Suggest ways that the duration can be shortened.