The learning rate of 0.90 on cumulative averages is realized when constructing metal storage tanks. The first unit took 1,400 hours to construct. After six units were constructed, the hunting season opened and the entire work crew took off a total of 5 days. Ignoring the impact of weekends, determine the time required to complete units 7 through 12. If wages are $10 per hour, what was the cost of the hunting season in terms of lost productivity?