Question

You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Ac
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1

A cost variance = Earned Value - Actual cost

Earned value = 20000

Actual Cost = 20000

Cost variance = 20000 - 20000 = 0

B schedule variance = earned value - planned value

earned value = 20000

planned value = 23000

schedule variance = 20000 - 23000

= -3000

Negative value means that we are behind schedule.

C cost performance index = Earned Value / Actual cost

= 20000/20000 = 1

When CPI is 1 , it means project is performing on budget

D schedule performance index = Earned value / planned value

= 20000/23000

= 0.869

This means that for every estimated hour of work, the team has completed only 0.8 hours i.e. 45 minutes

** As per HOMEWORKLIB POLICY, we can answer the first or specified question. Please re-post the remaining questions.

Add a comment
Know the answer?
Add Answer to:
You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Sketch (free-hand sketch acceptable) a graph to show the relationship between PV, AC, EV, BAC, and EAC. Interpret the sketch explaining on-budget (cost) and on-time (schedule) progress of the project. [75-150-word response.]

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Sketch (free-hand sketch acceptable) a graph to show the relationship between PV, AC, EV, BAC, and EAC. Interpret the sketch explaining on-budget (cost) and on-time (schedule) progress of the project. [75-150-word response.]

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it Page 6 of 8 IS8100-01 Fa2019 under or over budget? Use all of the calculated variances and indexes from above to support your argument. [50-100-word response.]

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT