3
a.
| Account Titles | Debit | Credit |
| Work in Process Inventory | $ 36,000 | |
| Raw Materials Inventory | $ 36,000 | |
| (Issued raw material to production) | ||
| Work in Process Inventory | $ 48,000 | |
| Wages Payable | $ 48,000 | |
| (Wages for production) | ||
| Work in Process Inventory | $ 60,000 | |
| Manufacturing Overhead | $ 60,000 | |
| (Manufacturing Overhead applied) |
b.
| Physical Units | |
| Units accounted for | |
| Completed and transferred out | 10500 |
| Ending Work in process | 6000 |
| Total Units accounted for | 16500 |
Units completed and transferred out = 4000 + 12500 - 6000 =
10500
c. Equivalent units of Production = Units completed + Ending WIP
x completion
Material = 10500 + 6000 x 100% = 16500
Labor = 10500 + 6000 x 70% = 14700
Overhead = 10500 + 6000 x 70% = 14700
As per HOMEWORKLIB RULES we are supposed to answer 1 question, i have, kindly post other question separately
av Normal No Spacing Ch 3 Homework Problem A The following data refer to a production...
Pablo Company calculates the cost for an equivalent unit of
production using process costing.
Data for June
Work-in-process inventory, June 1: 16,000
units
Direct materials: 100% complete
$
32,000
Conversion: 40% complete
12,800
Balance in work-in-process, June 1
$
44,800
Units started during June
39,200
Units completed and transferred out
39,200
Work-in-process inventory, June 30
16,000
Direct materials: 100% complete
Conversion: 80% complete
Costs incurred during June
Direct materials
$
90,160
Conversion costs
Direct labor
90,160
Applied overhead
121,520
Total...
Pablo Company calculates the cost for an equivalent unit of production using process costing. Data for June Work-in-process inventory, June 1: 21,000 units Direct materials: 100% complete Conversion: 40% complete Balance in work-in-process, June 1 Units started during June Units completed and transferred out Work-in-process inventory, June 30 Direct materials: 100% complete Conversion: 80% complete Costs incurred during June Direct materials Conversion costs Direct labor Applied overhead Total conversion costs $ 42,000 16,800 $ 58,800 50,200 50,200 21,000 $140,560 140,560...
Pablo Company calculates the cost for an equivalent unit of
production using process costing.
Data for June
Work-in-process inventory, June 1: 15,000
units
Direct materials: 100% complete
$
30,000
Conversion: 40% complete
12,000
Balance in work-in-process, June 1
$
42,000
Units started during June
37,000
Units completed and transferred out
37,000
Work-in-process inventory, June 30
15,000
Direct materials: 100% complete
Conversion: 80% complete
Costs incurred during June
Direct materials
$
81,400
Conversion costs
Direct labor
81,400
Applied overhead
111,000
Total...
Pablo Company calculates the cost for an equivalent unit of production using process costing. Data for June Work-in-process inventory, June 1: 25,000 units Direct materials: 100% complete $ 50,000 Conversion: 40% complete 20,000 Balance in work-in-process, June 1 $ 70,000 Units started during June 59,000 Units completed and transferred out 59,000 Work-in-process inventory, June 30 25,000 Direct materials: 100% complete Conversion: 80% complete Costs incurred during June Direct materials $ 188,800 Conversion costs Direct labor 188,800 Applied overhead 236,000 Total...
Pablo Company calculates the cost for an equivalent unit of production using costing. Data For June Work in process inventory, June 1: 30,000 units Direct materials: 100% complete 60,000 Conversation: 40% complete 25,000 Balance in work process 85,000 Units started during June 70,000 Units completed and transferred out 70,000 Work in process inventory, June 30 30,000 Direct materials: 100% complete Conservation: 80% complete Costs incurred during June Direct materials 122,500 Conversation costs Direct labor 119,720 Applied overhead 179,580 Total conversation...
Pablo Company calculates the cost for an equivalent unit of production using process costing. $ 30,000 12,000 $ 42,000 37,000 37,000 15,000 Data for June Work-in-process inventory, June 1: 15,000 units Direct materials: 100% complete Conversion: 40% complete Balance in work-in-process, June 1 Units started during June Units completed and transferred out Work-in-process inventory, June 30 Direct materials: 100% complete Conversion: 80% complete Costs incurred during June Direct materials Conversion costs Direct labor Applied overhead Total conversion costs $ 81,400...
Pablo Company calculates the cost for an equivalent unit of production using process costing. $ 48,000 19,200 $ 67,200 56,800 56,800 24,000 Data for June Work-in-process inventory, June 1: 24,000 units Direct materials: 100% complete Conversion: 40% complete Balance in work-in-process, June 1 Units started during June Units completed and transferred out Work-in-process inventory, June 30 Direct materials: 100% complete Conversion: 80% complete Costs incurred during June Direct materials Conversion costs Direct labor Applied overhead Total conversion costs $176,080 176,080...
Equivalent Units; Weighted-Average and FIFO Unit Cost Pablo Company calculates the cost for an equivalent unit of production using process costing. Data for June Work-in-process inventory, June 1: 30,000 units Direct materials: 100% complete Conversion: 40% complete Balance in work-in-process, June 1 Units started during June Units completed and transferred out Work-in-process inventory, June 30 Direct materials: 100% complete Conversion: 80% complete Cost incurred during June Direct materials Conversion costs Direct labor Applied overhead Total conversion costs $ 60,000 24,000...
ONLY THE HIGHLIGHTED PORTION IS INCORRECT. CAN
SOMEONE HELP?
Exercise 6-34 Equivalent Units; Weighted-Average and FIFO Equivalent Unit Cost Pablo Company calculates the cost for an equivalent unit of production using process costing. $ 44,000 17,600 $ 61,600 52,400 52,400 22,000 Data for June Work-in-process inventory, June 1: 22,000 units Direct materials: 100% complete Conversion: 40% complete Balance in work-in-process, June 1 Units started during June Units completed and transferred out Work-in-process inventory, June 30 Direct materials: 100% complete Conversion:...
Equivalent Units of Production: Average Cost Method The following information concerns production in the Finishing Department for May. The Finishing Department uses the average cost method. ACCOUNT Work in Process—Finishing Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit May 1 Bal., 15,500 units, 70% completed 62,000 31 Direct materials, 76,000 units 185,440 247,440 31 Direct labor 115,000 362,440 31 Factory overhead 116,800 479,240 31 Goods transferred, 80,600 units 461,032 18,208 31 Bal., ? units, 35% completed 18,208 a....