Question

D Question 21 1 pts You have a required return of 12%. A project that you are considering offers an IRR of 10.97%. Should you
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer to question number 21

  • Reject

Explanation

IRR is the rate at which the present value of all cash flows from the project equals to the initial investment. This is a position where there is no gain on loss from the project.

Decision Rule

If

Capital budgeting decision

IRR <Required Return

Reject the project

IRR =phpPyPs9a.png Required Return

Indifferent

IRR >Required Return

Accept the project

As per the question required rate is 12% and IRR is 10.97% i.e. IRR is less than Required rate so reject the project.

Answer to question number 22

  • Accept

Explanation

NPV is the difference between the present value of cash inflows and the present value of cash out flows over the life of the project.

Decision Rule

When

Capital budgeting decision

NPV > Zero

Accept the project

NPV< Zero

Reject the project

In the given question NPV is 56,478, which is more than 0 (Zero) so accept the project.

Add a comment
Know the answer?
Add Answer to:
D Question 21 1 pts You have a required return of 12%. A project that you...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 24 1 pts You are considering the following two mutually exclusive projects. Which project(s) should...

    Question 24 1 pts You are considering the following two mutually exclusive projects. Which project(s) should be recommended? Project A Project B Year Cash Flow Year Cash Flow 0 $75,000 0 -$70,000 1 $19,000 1 $10,000 2 $48,000 2 $16,000 3 $12,000 3 $72,000 Required rate of return: 10 percent (for A) 13 percent (for B) O accept project B and reject project A. accept both project A and project B. O reject both project A and project B. O...

  • 2 pts Question 5 Your required return is 10%. Should you accept a project with the...

    2 pts Question 5 Your required return is 10%. Should you accept a project with the following cash flows? 2 3 Year Cash Flow -$25 +$7 +$8 +$15 O Yes, because the NPV is $5. Yes, because the IRR is 12.45% Yes, because the IRR is 30%. No, because the IRR is only 8.48%. No, because the IRR is 10.31%

  • Question 1 5 pts What is WACC? Why is it important? O The firm's required return....

    Question 1 5 pts What is WACC? Why is it important? O The firm's required return. It is used as the discount rate in NPV and it is used to compare to IRR. O It is the required return on debt. O It is the firm's required return. If IRR is less than WACC, you should accept the project. O It is the required return on equity. Question 2 5 pts What are some of the issues with the payback...

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR Cash Flow.....($200).....$850.......($700).......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Reject the project because the NPV is less than zero b. Accept the project because the IRR is greater than zero c. Accept the project because the NPV is greater than zero d. Accept the project because the payback...

  • Question 2 1 pts The internal rate of return may be defined as Jh The discount...

    Question 2 1 pts The internal rate of return may be defined as Jh The discount rate that makes the project NPV equal to zero. The discount rate that makes the PV of the expected cash flows equal to the initial outlay. the market rate of interest less the risk free rate. a&b are both correct. a&care both correct Question 3 1 pts For independent projects, the NPV method and the IRR method will always lead to the same accept/reject...

  • Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is...

    Question 10 7.5 pts You are considering a project with conventional cash flows. The IRR is 15.7 percent, NPV is -$198, and the payback period is 3.92 years. Which one of the following statements is correct given this information? This project should be accepted based on the internal rate of return. The discount rate used in computing the net present value was less than 15.7 percent. The required rate of return must be greater than 15.7 percent. The discounted payback...

  • You are analyzing a project and have prepared the following data: Year Cash Flow $169,000 $46,200...

    You are analyzing a project and have prepared the following data: Year Cash Flow $169,000 $46,200 I$87,300 $41,000 I$39,000 1 12 4 Required payback period 2.5 years Required return 8.50% the project. Based on the profitability index of 0.97; accept for this project, you should 1.05; accept 1.18; accept 0.97; reject 1.05; reject Question 15 You are analyzing a project and have prepared the following data: Year Cash Flow $169,000 $46,200 $87,300 $41,000 $39,000 Required payback period 2.5 years Required...

  • 3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should...

    3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent? Year Project A Project B -$80,000 -$80,000 31,000 31,000 0 31,000 110,000 A. accept project A as it always has the higher NPV B. accept project B as it always has the higher NPV C. accept A at 8.5 percent and B at 13 percent D. accept...

  • 1) Suppose that you calculate the NPV of a project, and obtain a value of $100...

    1) Suppose that you calculate the NPV of a project, and obtain a value of $100 million dollars. After completing your analysis, you find out that the corporate tax rate will change from 40% to 30%. If nothing else changes, what is the effect of this tax change on the NPV you had calculated? Assume that your company has no debt. a) The new NPV will be lower than $100 b) The new NPV will be higher than $100 c)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT